System for supporting carry-in operation planning
    1.
    发明授权
    System for supporting carry-in operation planning 失效
    支持运载计划的系统

    公开(公告)号:US08326664B2

    公开(公告)日:2012-12-04

    申请号:US13151540

    申请日:2011-06-02

    CPC classification number: G06Q10/06 G06Q10/063116 G06Q10/063118 G06Q10/1097

    Abstract: A carry-in ready period calculation part calculates a candidate of a carry-in ready period which is a period during which a carry-in operation can be conducted and outputs the candidate in an output part so as to make entire construction works efficient. The calculation is performed based on a site arrival time schedule which is a time schedule showing when a carry-in target equipment arrives at a site, a temporary placement time schedule which is a time schedule showing when the equipment arrived is temporarily placed, and a construction time schedule of a building in which the equipment is carried.

    Abstract translation: 进入就绪期间计算部分计算作为可以进行携带操作的期间的入库就绪期间的候选,并且在输出部输出候选,以使整个构造工作有效。 该计算是基于作为进入目标设备到达现场的时间表的站点到达时间表进行的,作为暂时放置设备到达时间的时间表的临时放置时间表,和 设备运载的建筑物的施工时间表。

    SYSTEM FOR SUPPORTING CARRY-IN OPERATION PLANNING
    2.
    发明申请
    SYSTEM FOR SUPPORTING CARRY-IN OPERATION PLANNING 失效
    支持运行规划的系统

    公开(公告)号:US20110301995A1

    公开(公告)日:2011-12-08

    申请号:US13151540

    申请日:2011-06-02

    CPC classification number: G06Q10/06 G06Q10/063116 G06Q10/063118 G06Q10/1097

    Abstract: A carry-in ready period calculation part calculates a candidate of a carry-in ready period which is a period during which a carry-in operation can be conducted and outputs the candidate in an output part so as to make entire construction works efficient. The calculation is performed based on a site arrival time schedule which is a time schedule showing when a carry-in target equipment arrives at a site, a temporary placement time schedule which is a time schedule showing when the equipment arrived is temporarily placed, and a construction time schedule of a building in which the equipment is carried.

    Abstract translation: 进入就绪期间计算部分计算作为可以进行携带操作的期间的入库就绪期间的候选,并且在输出部输出候选,以使整个构造工作有效。 该计算是基于作为进入目标设备到达现场的时间表的站点到达时间表进行的,作为暂时放置设备到达时间的时间表的临时放置时间表,和 设备运载的建筑物的施工时间表。