- 专利标题: Underground mining method for unexploited coal in boundary open-pit mine
-
申请号: US18159102申请日: 2023-01-25
-
公开(公告)号: US11821314B2公开(公告)日: 2023-11-21
- 发明人: Shuzhao Chen , Fuming Liu , Bo Chang
- 申请人: CHINA UNIVERSITY OF MINING AND TECHNOLOGY , Xinjiang Tianchi Energy Co., Ltd. , China Energy Group Xinjiang Energy Company Ltd
- 申请人地址: CN Xuzhou
- 专利权人: CHINA UNIVERSITY OF MINING AND TECHNOLOGY,XINJIANG TIANCHI ENERGY CO., LTD.,CHINA ENERGY GROUP XINJIANG ENERGY COMPANY LTD
- 当前专利权人: CHINA UNIVERSITY OF MINING AND TECHNOLOGY,XINJIANG TIANCHI ENERGY CO., LTD.,CHINA ENERGY GROUP XINJIANG ENERGY COMPANY LTD
- 当前专利权人地址: CN Xuzhou; CN Changji Prefecture; CN Urumqi
- 代理机构: Bayramoglu Law Offices LLC
- 优先权: CN 2210096686.3 2022.01.26
- 主分类号: E21C41/18
- IPC分类号: E21C41/18 ; E21C41/28 ; E21C41/32 ; E02D17/20 ; C02F103/10
摘要:
An underground mining method for unexploited coal in a boundary open-pit mine is provided. A shaft construction platform is arranged at one rock step to two rock steps above a coal seam. Intermediate bridges are built starting from a pit bottom. Mining area clay is laid on a working slope where no intermediate bridge is built and on a side slope with an outcrop of the coal seam as a sealing layer to seal the slopes. Auxiliary vertical shafts and main inclined shafts are dug. The pit bottom is dug downward to form a digging space on a side close to the working slope between two adjacent ones of the intermediate bridges, and clay is filled into the digging space to form an artificial water barrier layer. A roadway communicating the main inclined shafts and the auxiliary vertical shafts is constructed, and a coal seam stope face is arranged.