CPC分类号: E21C41/16 , E21B43/26 , E21F13/04 , E21F13/066
摘要: A method useful in the continuous ore extraction in underground works intended for the permanent production of extraction from draw points or trenches, comprising the construction of reduced size drifts (4) wherein through the center defined by a group of drifts crosses a drift (2) which is intended for ore haulage, such drift crosses successively all drift groups defined at the exploitation face,—such extraction points (11) are arranged to form a regular layout [m4] at certain distances which are compatible with an interactive gravitational flow; once such drifts, trenches and haulage drifts are constructed the pre-conditioning, caving and extraction stages are carried out.
-