公开(公告)号:KR1020180002131A
公开(公告)日:2018-01-08
申请号:KR1020160081124
申请日:2016-06-28
申请人: 코스피 주식회사
IPC分类号: E04C5/12
摘要: 본발명은재인장가능하게구성되는재인장커플러유닛에있어, 커플러유닛의볼륨을줄여커플러유닛에의한하중부담을줄이고, 재인장과정을간소화할수 있는재인장커플유닛에관한것으로, 본발명은선단부중심을통해인장재가관통되고, 내부에상기인장재의고정공간이형성되는하우징과; 상기하우징내부의인장재에고정되어, 상기인장재가상기하우징외측으로이동되는것을제한하는고정수단과; 일단부가상기하우징후단부와고정되는재인장바를포함하여구성된다. 이와같은본 발명에의하면, 본발명에서는정착부정착력발생부분과재인장결합부를이원화시켜커플러의볼륨이슬림화되고, 이에따라개별부재에부담되는하중이저하되는효과가있다.
摘要翻译: 在识别场耦合器单元中的本发明,其被构造成场识别,降低了耦合器单元的容积,以减少由再片过程的耦合器单元承受的载荷被重新场耦合单元具有简化,本发明是前端 拉伸材料穿过中心穿过的壳体以及形成在拉伸材料中的拉伸材料的固定空间; 固定装置固定在外壳内的拉伸材料上,以限制拉伸材料在外壳外面的移动; 还有一根钢筋,其一端固定在外壳的后端。 这样,根据本发明,并且本发明中,通过发生双负粘附耦合器固定部的薄型化的体积和部分重新组合部分,yiettara则存在个别构件上的载荷负担降低的效果。
-
公开(公告)号:KR1020160099150A
公开(公告)日:2016-08-22
申请号:KR1020150020895
申请日:2015-02-11
摘要: 거더내부에매립되는정착구에긴장후 정착되는앵커헤드의중심축을서로용이하게일치시킬수 있도록하여프리스트레스도입효과를증진시킬수 있는긴장재중심축조정용정착장치를이용한거더교시공방법에관한것으로서, 상기긴장재중심축조정용정착장치는정착판을포함하는정착구; 상기정착판에지지되는앵커헤드; 및앵커헤드와앵커헤드지지블록이서로점 접촉또는면 접촉되는수평블록및 상기수평블록과일체로형성되어정착판에고정설치되는확장수평블록;을포함하여구성된다.
摘要翻译: 本发明提供了一种通过使用用于腱轴调整的锚固装置来构造梁桥的方法,以便容易地匹配锚定在锚定在大梁内侧的锚固装置中的锚定头的轴线以提高预应力 介绍效果。 根据本发明,用于腱轴调整的锚固装置包括:锚固装置,包括锚固板; 由锚固板支撑的锚头; 以及锚固头支撑块,其包括水平块,其中锚固头和锚固头支撑块彼此进入或表面接触;以及延伸的水平块,其与水平块一体地形成以被固定并安装在锚固 盘子。
-
公开(公告)号:KR1020160004399A
公开(公告)日:2016-01-12
申请号:KR1020157036070
申请日:2014-05-30
申请人: 파우에스엘 인터나치오날 아게
摘要: 본발명의케이블앵커리지는축 방향의장력에대항하여, 케이블, 예컨대복수의스트랜드를포함하는인장케이블을고정하도록설계되며, 각스트랜드(50)는수증기침투에대항하여앵커리지의개별채널(60)에개별적으로봉인되며, 각스트랜드는개별적으로제거및 교체될수 있다. 조임탄성환형실(26)은채널에서리세스(27) 안에끼워진다. 환형실(27)은앵커리지의앵커블록단부(1)로부터삽입된다.
-
公开(公告)号:KR101524977B1
公开(公告)日:2015-06-02
申请号:KR1020140047279
申请日:2014-04-21
申请人: 고재용
发明人: 고재용
CPC分类号: E01D19/103 , E01D19/04 , E01D19/14 , E01D21/065 , E04C5/12
摘要: 본발명에따른교량점검로프레임은, 교각(1)의측면에앵커체결되고, 서로나란한두 개의고정판이돌출형성되는앵커받침대(110); 고정판(110)에체결됨으로써교각(1)의측면에서바깥쪽으로뻗어나가도록앵커받침대(110)에연결설치되며, 좌우양측에는오목한가이드라인홈(125)이길이방향으로길게형성되는브라켓(120); 좌우양단에각각위로올라가다가안쪽으로절곡되는절곡부(131)의끝부분이가이드라인홈(125)에끼워지도록설치되는슬라이더(130); 및한쪽끝단은슬라이더(130)에힌지결합되고나머지다른한쪽끝단은앵커받침대(110)에힌지결합되는슬라이더고정대(130); 를포함하여이루어지는것을특징으로한다. 본발명에의하면, 교량점검로(100)를교각(1)의측면에설치함에있어서교각(1)의다양한측면기울기에대하여용이하게수평설치할수 있을뿐만아니라무거운하중에대해서도교량점검로(100)가바깥쪽으로기울어지거나붕괴되지않고본래의상태그대로잘 버틸수 있게된다. 특히, 본발명은압출방식으로제조되는관 형상의브라켓(120)을사용하기때문에프레임자체무게가매우가볍고, 또한브라켓(120)의단부를가공하여기울기를부여하기만하면교각(1)의측면경사에상관없이교량점검로(100)를수평하게설치할수 있다는점에서매우유용하다.
摘要翻译: 根据本发明的桥梁检查路径框架的特征在于包括锚固固定在桥(1)的侧表面上并具有彼此平行的突出固定板的锚固支撑件(110) 连接到所述锚固支撑件(110)的托架(120),以通过固定到所述固定板(115)并且沿纵向方向具有凹入的引导槽(125)从所述桥(1)的侧表面延伸到外侧 左右两侧; 滑动件(130),其能够使从左右端部向上方突出的弯曲单元(131)的端部向内侧弯曲成与所述引导槽(125)嵌合的前端部; 和滑块固定架(140),其一端铰接于滑块(130),另一端铰链连接到锚固支架(110)上。 根据本发明,桥梁检查路径100能够在将桥梁检查路径(100)安装在桥的侧表面(100)上时能够水平安装,尽管桥(1)具有各种侧面倾斜 1),并承受沉重的载荷,而不会向外倾斜或塌陷。 特别地,本发明使用通过挤压方法制造的管状托架(120),使得框架的重量较轻。 此外,本发明有利的是水平地安装桥梁检查路径(100),而不管桥(1)的横向坡度如何。
-
公开(公告)号:KR1020150005959A
公开(公告)日:2015-01-15
申请号:KR1020147031145
申请日:2012-04-05
申请人: 소레탄체 프레씨네트
CPC分类号: E01D19/14 , E01D21/00 , E04C5/12 , F16J15/021 , Y10T29/49826
摘要: 본 발명은 케이블 앵커 장치(4)는 구조 요소(1, 3)에 적어도 하나의 케이블(2)을 고정하기 위해서 배열되고 구조 요소의 개구(6)를 마주보는 전면(15)을 구비하며, 적어도 하나의 케이블(2)은 전면을 통하여 구조 요소의 외부로 연장하며, 씰은 앵커 장치(4)의 적어도 전면(15)을 포함하는 고정된 케이블(2)의 밀폐부의 경계에 구조 요소의 개구(6)를 포함하는 구조 요소의 표면의 경계로부터 연장하는 슬리브(12)를 포함하는 케이블 앵커 장치(4)를 구조 요소(1, 3)에 봉인하기 위한 씰 및 실링 방법에 관한 것이다.
-
公开(公告)号:KR101450136B1
公开(公告)日:2014-10-21
申请号:KR1020097025322
申请日:2007-12-03
申请人: 프라데라 페리세아 카를로스
发明人: 프라데라페리세아카를로스
CPC分类号: E04C5/08 , B28B5/04 , B28B7/0064 , B28B7/364 , B28B11/245 , B28B11/247 , B28B23/0056 , B28B23/0062 , B28B23/043 , E04C2/06 , E04C5/12 , E04C2002/002
摘要: 프리스트레스트 2축 강화재를 구비한 시멘트 몰타르 패널은, 2 내지 7 cm 범위의 두께를 가지며 2축 강화재를 포함하는 시멘트 몰타르의 슬래브에 의해 형성된다. 상기 슬래브는 패널 조립체의 조작 및/또는 빌딩 구조물에의 고정을 가능케 하는 다용도 조작을 위한 수단을 시멘트 몰타르 덩어리 내에 은닉시키며, 상기 다용도 작동 수단은 일측 편에서는 세팅된 시멘트 몰타르 덩어리에 그것들을 고정하기 위한 수단을 구성하며, 반대편 타측 편에서는 패널 조작 수단을 위한, 또는 상기 빌딩 구조물에 대한 그것의 고정을 위한 부재들을 위한 고정 수단을 구성한다.
시멘트 몰타르 패널, 프리스트레스트 강화재, 다용도, 다목적, 조작 수단-
公开(公告)号:KR101411348B1
公开(公告)日:2014-06-25
申请号:KR1020130092012
申请日:2013-08-02
申请人: 주식회사 씨포트
发明人: 홍경표
CPC分类号: E01D15/14 , B63B35/34 , E01D15/24 , E01D19/14 , E01D2101/24 , E04C5/12 , E04C2003/0452 , E04C2003/0473
摘要: The present invention relates to a concrete pontoon, and more particularly, to a concrete pontoon which includes a connection device connecting a plurality of concrete floating bodies by means of connection frames using C-shaped steel members embedded into the top surface of each concrete floating body and coupling members sliding along the C-shaped steel members, wherein the connection work is simple and the plurality of concrete floating bodies is easily connected in horizontal and vertical directions thereof, even if the difference between the qualities exists in the concrete floating bodies, thereby enabling users to construct various floating buildings and marinas, without having any separate manufacturing, improving stability through the integration of the concrete floating bodies with the C-shaped steel members and the connection frames, and miniaturizing the concrete floating bodies through the simple connection work.
摘要翻译: 本发明涉及一种混凝土浮筒,更具体地涉及一种混凝土浮筒,该混凝土浮筒包括连接装置,该连接装置借助连接框架连接多个混凝土浮体,所述连接框架使用嵌入每个混凝土浮体的顶表面中的C形钢构件 以及沿着C形钢构件滑动的联接构件,其中连接工作简单,并且多个混凝土浮体容易地在其水平和垂直方向上连接,即使在混凝土浮体中存在质量差异,因此 使用户能够构建各种浮动建筑物和码头,而无需单独制造,通过将混凝土浮体与C形钢构件和连接框架结合在一起,提高稳定性,并通过简单的连接工作使混凝土浮体小型化。
-
公开(公告)号:KR101407990B1
公开(公告)日:2014-06-17
申请号:KR1020130154018
申请日:2013-12-11
申请人: (주)유안개발
发明人: 손승오
IPC分类号: E01D22/00 , E01D19/06 , E01C11/02 , E04B1/68 , E01D19/14 , E04C5/12 , E01D101/24 , E01D101/40 , E01D101/34
CPC分类号: E01D22/00 , E01C11/02 , E01D19/06 , E01D19/14 , E01D2101/24 , E01D2101/34 , E01D2101/40 , E04B1/68 , E04C5/12
摘要: The present invention relates to a method for replacing post-placing concrete of an expansion joint, and a post-placing structure of an expansion joint. According to the present invention, a first cover plate is installed after a damaged part of the post-placing concrete of the expansion joint of a bridge is removed, and a second cover plate to able to be detached from the upper part of the first cover plate is installed. Therefore, durability and sliding prevention effect can be improved. According to the present invention, the method for replacing post-placing concrete of an expansion joint to replace post-placing concrete of an expansion joint finished by placing post-placing concrete in the upper part of reinforcement steel after installing the expansion joint between a pair of structures connected with each other, and installing the reinforcement steel comprises a post-placing concrete removing step for forming installation space by removing the post-placing concrete; a first cover plate installing step for installing the first cover plate in the upper part of the reinforcement steel; and a second cover plate installing step for installing the second cover plate in the upper part of the first cover plate. The second cover plate is characterized by being detached from the upper part of the first cover plate.
摘要翻译: 本发明涉及一种更换膨胀节的后置混凝土的方法和膨胀节的后置结构。 根据本发明,在桥的伸缩接头的后置混凝土的损坏部分被去除之后安装第一盖板,并且第二盖板能够从第一盖的上部分离 安装板。 因此,可以提高耐久性和滑动防止效果。 根据本发明,用于更换膨胀接头的后置混凝土的方法来代替在将一对膨胀接头安装在一对之后,通过将后置混凝土放置在钢筋的上部而将膨胀接头的后置混凝土 相互连接的结构,并且安装钢筋包括:后置混凝土除去步骤,用于通过移除后置混凝土来形成安装空间; 第一盖板安装步骤,用于将第一盖板安装在钢筋的上部; 以及第二盖板安装步骤,用于将第二盖板安装在第一盖板的上部。 第二盖板的特征在于从第一盖板的上部分离。
-
公开(公告)号:KR101341847B1
公开(公告)日:2013-12-16
申请号:KR1020130041397
申请日:2013-04-16
发明人: 유문식
IPC分类号: E01D19/04 , E01D22/00 , E01D19/14 , F16F15/02 , F16F7/104 , E04B1/36 , E04C5/12 , E01D101/26
CPC分类号: E01D19/041 , E01D19/14 , E01D22/00 , E01D2101/26 , E04B1/36 , E04C5/12 , F16F7/104 , F16F15/02
摘要: The present invention relates to an anti-seismic reinforcement device of a bridge using function-separated supports, and an anti-seismic reinforcement method using such a device. The purpose of the present invention is to implement stable anti-seismic reinforcement for vertical and horizontal movements in an earthquake by attaching an anti-seismic reinforcement device to the side of a girder. For the anti-seismic reinforcement device of a bridge, which is installed for the anti-seismic reinforcement of a girder (30, 60) which is supported by a bridge support (20) on top of a pier (10), according to the present invention to achieve such a purpose, a reinforcement support (40) made of rubber with fixed elasticity is fixed to both sidewalls of the girder (30, 60) in a symmetrical shape; a reaction force stand (50) for supporting horizontal movements is fixed to the top of the pier (10) at the outer side of the reinforcement support (40); and a vertical plate (51), which is combined with the reinforcement support (40), and a horizontal plate (52), which is combined with the pier (10) by using anchors, form an integrated structure for the reaction force stand (50), and therefore the reaction force stand (50) has an L-shaped cross-sectional structure.
摘要翻译: 本发明涉及使用功能分离的支架的桥梁的抗震加固装置,以及使用这种装置的抗震加固方法。 本发明的目的是通过将抗震加固装置附接到大梁的侧面来实现用于地震中垂直和水平运动的稳定的抗震加固。 对于桥梁的抗震加固装置,其安装用于由在桥墩(10)顶部的桥架(20)支撑的梁(30,60)的抗震加固件,根据 为了实现这一目的,将具有固定弹性的橡胶制的加强支撑件(40)以对称的形状固定在梁(30,60)的两个侧壁上; 用于支撑水平运动的反作用支架(50)在加强支撑件(40)的外侧固定到码头(10)的顶部; 以及与加强支撑件(40)组合的垂直板(51)和通过使用锚固件与墩(10)组合的水平板(52)形成用于反作用力支架的一体结构( 50),因此反作用力台(50)具有L形横截面结构。
-
公开(公告)号:KR1020130102163A
公开(公告)日:2013-09-17
申请号:KR1020120023161
申请日:2012-03-07
申请人: 아이씨비 주식회사 , 한국씨엠이엔지(주)
摘要: PURPOSE: A concrete girder for the upper structure of a bridge is provided to facilitate the tensile reinforcement of a concrete member and to prevent the rigidity degradation of a post tensile reinforcing material due to corrosion. CONSTITUTION: A concrete girder (11) for the upper structure of a bridge comprises a concrete member and a post tensile reinforcing anchor (30) embedded into the concrete member. The post tensile reinforcing anchor includes an anchor plate, a bolt fastening column, and an anchor bolt. The bolt fastening column is formed on the bottom of the anchor plate and is formed with bolt grooves in the longitudinal direction. The anchor bolt is joined to the bolt fastening column to be screwed to a bolt groove. The anchor bolt is embedded into the concrete member with the head exposed to the outer surface of the concrete member.
摘要翻译: 目的:提供一种用于桥梁上部结构的混凝土梁,以便于混凝土构件的拉伸加强,并防止由于腐蚀引起的后拉伸增强材料的刚性退化。 构成:用于桥梁上部结构的混凝土梁(11)包括混凝土构件和嵌入混凝土构件的后拉伸增强锚固件(30)。 后拉伸增强锚固件包括锚板,螺栓紧固柱和锚栓。 螺栓紧固柱形成在锚板的底部,并且在纵向方向上形成有螺栓槽。 锚定螺栓连接到螺栓紧固柱上以螺纹连接到螺栓槽。 将锚杆螺栓嵌入混凝土构件中,头部暴露于混凝土构件的外表面。
-
-
-
-
-
-
-
-
-