METHOD AND ARRANGEMENT FOR CONFIGURING A SYSTEM FOR MONITORING THE PERFORMANCE OF A CONTROL LOOP OF AN INDUSTRIAL PLANT
    1.
    发明申请
    METHOD AND ARRANGEMENT FOR CONFIGURING A SYSTEM FOR MONITORING THE PERFORMANCE OF A CONTROL LOOP OF AN INDUSTRIAL PLANT 有权
    用于配置用于监测工业控制环的性能的系统的方法和装置

    公开(公告)号:US20140249655A1

    公开(公告)日:2014-09-04

    申请号:US14278718

    申请日:2014-05-15

    CPC classification number: G05B23/0264 G05B23/0297

    Abstract: Exemplary embodiments for configuring a system for monitoring the performance of a control loop of an industrial plant includes reading in first process data derived from measurements of at least one sensor inside the control loop during a specified control situation, calculating from the first process data a corresponding at least one performance index indicating the behaviour of the control loop and determining a first quality of the control performance depending on the difference between the at least one performance index and a corresponding threshold value. In case that the first quality of the control performance is determined to be less than good, a second quality of the control performance is determined either by calculating the second quality from an analysis of second process data or by processing a user input from a user of the system which indicates the second quality.

    Abstract translation: 用于配置用于监视工业设备的控制环路的性能的系统的示例性实施例包括:在指定的控制状况期间读取从控制回路内的至少一个传感器的测量得到的第一过程数据,从第一过程数据计算相应的 指示所述控制循环的行为的至少一个性能指标,并且根据所述至少一个性能指标与相应的阈值之间的差异确定所述控制性能的第一质量。 在控制性能的第一质量被确定为小于良好的情况下,通过从第二处理数据的分析计算第二质量或通过处理来自用户的用户输入来确定控制性能的第二质量 表示第二个质量的系统。

    SYSTEMS AND METHODS FOR OPTIMIZED OPERATION OF AN INDUSTRIAL PRODUCTION OR MANUFACTURING FACILITY
    2.
    发明申请
    SYSTEMS AND METHODS FOR OPTIMIZED OPERATION OF AN INDUSTRIAL PRODUCTION OR MANUFACTURING FACILITY 审中-公开
    优化操作工业生产或制造设施的系统和方法

    公开(公告)号:US20140303798A1

    公开(公告)日:2014-10-09

    申请号:US14308358

    申请日:2014-06-18

    CPC classification number: G06Q50/06 G06Q10/00

    Abstract: A production planning system and a system for energy supply planning are configured to determine a production schedule and an energy supply schedule, respectively, by interactively and mutually exchanging scheduling information with the respective other system and by taking the received scheduling information into account during the planning of the respective schedule. The interacting is performed in a kind of handshaking during planning of the respective schedules, where each of the two systems waits with the next iteration step until the other system delivers its updated schedule.

    Abstract translation: 配置生产计划系统和能量供应计划系统,分别通过与相应的其他系统交互地和相互交换调度信息来确定生产计划和能量供应计划,并且通过在规划期间考虑收到的调度信息 的时间表。 在规划各个时间表期间,交互是以一种握手方式进行的,其中两个系统中的每一个在下一个迭代步骤中等待,直到另一个系统发送其更新的时间表。