    地下管道无缝铺设

    公开(公告)号:US3589135A

    公开(公告)日:1971-06-29

    申请号:US3589135D

    申请日:1969-03-13

    CPC classification number: E02F5/101 E02F5/102 F16L1/032

    Abstract: A method of laying lengths of underground pipe, for example drainage pipes, by forming an underground tunnel by means of a mole plough, and drawing a length of pipe into the tunnel into its required final position, characterized in that a liquid slurry is injected into the tunnel formed by the mole before the pipe length is drawn into the tunnel, the slurry serving to lubricate the pipe during its travel along the tunnel. Preferably the principal ingredient of the slurry is Bentonite. The pipe may be towed directly behind the mole and drawn progressively into the tunnel as it is formed or the pipe may be drawn into the slurry-filled tunnel after the mole plough has completed its traverse.