1.
公开(公告)号:US08955302B2
公开(公告)日:2015-02-17
申请号:US13783911
申请日:2013-03-04
Applicant: Alstom Technology Ltd
Inventor: Floris Van Straaten , Juergen Hoffmann
CPC classification number: F02C6/18 , F02C3/13 , F02C3/34 , F02C9/18 , F05D2220/60 , F05D2260/61 , F05D2270/08 , Y02E20/16
Abstract: A method and gas turbine are provided for the reliable purging of an exhaust gas recirculation line of the gas turbine with exhaust gas recirculation without the use of additional blow-off fans. A blow-off flow of the compressor is used for the purging of the exhaust gas recirculation line. The gas turbine can include at least one purging line which connects a compressor blow-off point to the exhaust gas recirculation line.
Abstract translation: 提供了一种方法和燃气轮机,用于可靠地清除燃气轮机的废气再循环管线,其中废气再循环,而不使用额外的吹风扇。 压缩机的吹出流被用于净化排气再循环管线。 燃气轮机可以包括将压缩机吹出点连接到废气再循环管线的至少一个清洗管线。
-
公开(公告)号:US20130249213A1
公开(公告)日:2013-09-26
申请号:US13850340
申请日:2013-03-26
Applicant: ALSTOM TECHNOLOGY LTD
Inventor: Joerg Oesterheld , Juergen Hoffmann
IPC: H02P9/08
CPC classification number: H02P9/08 , F01D19/00 , F02C7/26 , F02C9/18 , F05D2220/764 , F05D2260/85 , F05D2270/061
Abstract: The invention relates to a method for the start of a power plant installation (10), which comprises a gas turbine (2), a generator (18) coupled to the gas turbine (2), and a frequency converter (27) to feed current into an electrical grid (1). In accordance with the method, during the start of the gas turbine (2), the generator (18) is connected to the electrical grid (1) via the frequency converter (27) before the operating rotational speed of the gas turbine (2) is reached, wherein the frequency converter (27) is controlled such that it generates an output current with the grid frequency. The invention further relates to a power plant installation (10) for the execution of such a method.
Abstract translation: 本发明涉及一种用于启动发电厂安装(10)的方法,其包括燃气轮机(2),联接到燃气轮机(2)的发电机(18)和用于馈送 电流进入电网(1)。 根据该方法,在燃气轮机(2)启动期间,在燃气轮机(2)的操作转速之前,发电机(18)经由变频器(27)连接到电网(1) ,其中所述变频器(27)被控制成使得其产生具有所述电网频率的输出电流。 本发明还涉及一种用于执行这种方法的发电厂安装(10)。
-
公开(公告)号:US09708983B2
公开(公告)日:2017-07-18
申请号:US14501651
申请日:2014-09-30
Applicant: ALSTOM Technology Ltd
Inventor: Adnan Eroglu , Juergen Hoffmann
CPC classification number: F02C9/26 , F02C3/14 , F02C9/263 , F02C9/28 , F23C6/047 , F23N1/002 , F23N2027/10 , F23N2037/02 , F23N2041/20 , F23R3/34 , F23R3/346 , F23R2900/03341
Abstract: The present disclosure refers to a method for operating a gas turbine with sequential combustors having a first-burner, a first combustion chamber, and a second combustor arranged sequentially in a fluid flow connection. To minimize emissions and combustion stability problems during transient changes when the fuel flow to a second combustor is initiated the method includes the steps of increasing the second fuel flow to a minimum flow, and reducing the first fuel flow to the first-burner of the same sequential combustor and/or the fuel flow to at least one other sequential combustor of the sequential combustor arrangement in order keep the total fuel mass flow to the gas turbine substantially constant. Besides the method a gas turbine with a fuel distribution system configured to carry out such a method is disclosed.
-
公开(公告)号:US08916985B2
公开(公告)日:2014-12-23
申请号:US13850340
申请日:2013-03-26
Applicant: ALSTOM Technology Ltd
Inventor: Joerg Oesterheld , Juergen Hoffmann
CPC classification number: H02P9/08 , F01D19/00 , F02C7/26 , F02C9/18 , F05D2220/764 , F05D2260/85 , F05D2270/061
Abstract: A method for the start of a power plant installation which includes a gas turbine, a generator coupled to the gas turbine, and a frequency converter to feed current into an electrical grid. In accordance with the method, during the start of the gas turbine, the generator is connected to the electrical grid via the frequency converter before the operating rotational speed of the gas turbine is reached, wherein the frequency converter is controlled such that it generates an output current with the grid frequency. A power plant installation can execute the above method.
Abstract translation: 一种用于启动发电厂安装的方法,其包括燃气轮机,连接到燃气轮机的发电机和用于将电流馈入电网的变频器。 根据该方法,在燃气轮机起动期间,在达到燃气轮机的操作转速之前,发电机通过变频器连接到电网,其中变频器被控制成使其产生输出 电流与电网频率。 电厂安装可以执行上述方法。
-
公开(公告)号:US20130174535A1
公开(公告)日:2013-07-11
申请号:US13783911
申请日:2013-03-04
Applicant: Alstom Technology Ltd
Inventor: Floris VAN STRAATEN , Juergen Hoffmann
IPC: F02K3/02
CPC classification number: F02C6/18 , F02C3/13 , F02C3/34 , F02C9/18 , F05D2220/60 , F05D2260/61 , F05D2270/08 , Y02E20/16
Abstract: A method and gas turbine are provided for the reliable purging of an exhaust gas recirculation line of the gas turbine with exhaust gas recirculation without the use of additional blow-off fans. A blow-off flow of the compressor is used for the purging of the exhaust gas recirculation line. The gas turbine can include at least one purging line which connects a compressor blow-off point to the exhaust gas recirculation line.
-
-
-
-