Operation method of nuclear power plant
    1.
    发明授权
    Operation method of nuclear power plant 有权
    核电厂运行方式

    公开(公告)号:US07997078B2

    公开(公告)日:2011-08-16

    申请号:US12574219

    申请日:2009-10-06

    IPC分类号: G21D5/00 F01K7/34

    摘要: In a nuclear power plant, thermal power in a second operation cycle of a nuclear reactor is uprated from thermal power in a first operation cycle preceding the second operation cycle by at least one operation cycle. A proportion of steam extracted from a steam system and introduced to a feedwater heater, which is in particular extracted from an intermediate point and an outlet of a high pressure turbine, with respect to a flow rate of main steam, is reduced in the second operation cycle from that in the first operation cycle such that the temperature of feedwater discharged from the feedwater heater is lowered by 1° C. to 40° C. in the second operation cycle.

    摘要翻译: 在核电站中,核反应堆的第二操作循环中的热功率在第二操作周期之前的第一操作周期内从热功率上升至少一个操作周期。 在蒸汽系统中提取的蒸汽的比例相对于主蒸汽的流量被引入特定从高压汽轮机的中间点和出口抽出的给水加热器在第二操作 循环,从而在第二操作循环中使得从给水加热器排出的给水温度降低1℃至40℃。

    Operation method of nuclear power plant
    2.
    发明申请
    Operation method of nuclear power plant 有权
    核电厂运行方式

    公开(公告)号:US20070000250A1

    公开(公告)日:2007-01-04

    申请号:US11340643

    申请日:2006-01-27

    IPC分类号: G21D5/00

    摘要: A nuclear power plant and an operation method of the nuclear power plant, which can uprate plant power without greatly modifying the construction of plant equipment, while keeping a core's pressure loss characteristic, a safety margin, and a design margin in the transient state substantially the same as those before the power uprate. Thermal power in a second operation cycle of a nuclear reactor is uprated from thermal power in a first operation cycle preceding the second operation cycle at least one operation cycle. A proportion of steam extracted from a steam system and introduced to a feedwater heater, which is in particular extracted from an intermediate point and an outlet of a high pressure turbine, with respect to a flow rate of main steam is reduced in the second operation cycle from that in the first operation cycle such that temperature of feedwater discharged from the feedwater heater lowers in the range of 1° C. to 40° C. in the second operation cycle.

    摘要翻译: 一个核电站和核电厂的运行方式,可以在不大幅度修改工厂设备的情况下,提高设备功率,同时保持核心的压力损失特性,安全裕量和瞬态状态下的设计余量 与上电前相同。 核反应堆的第二操作循环中的热功率在第二操作循环之前的第一操作循环中从热功率升高至少一个操作周期。 在第二操作循环中,相对于主蒸汽的流量,从蒸汽系统提取并被引入特定从高压涡轮的中间点和出口抽出的给水加热器的一部分蒸汽减少 从第一操作循环中的过程中,使得从给水加热器排出的给水温度在第二操作循环中在1℃至40℃的范围内降低。

    Operation method of nuclear power plant
    3.
    发明授权
    Operation method of nuclear power plant 有权
    核电厂运行方式

    公开(公告)号:US08291704B2

    公开(公告)日:2012-10-23

    申请号:US13046329

    申请日:2011-03-11

    IPC分类号: G21D5/00 F01K7/34

    摘要: In a nuclear power plant, thermal power in a second operation cycle of a nuclear reactor is uprated from thermal power in a first operation cycle preceding the second operation cycle by at least one operation cycle. A proportion of steam extracted from a steam system and introduced to a feedwater heater, which is in particular extracted from an intermediate point and an outlet of a high pressure turbine, with respect to a flow rate of main steam, is reduced in the second operation cycle from that in the first operation cycle such that the temperature of feedwater discharged from the feedwater heater is lowered by 1° C. to 40° C. in the second operation cycle.

    摘要翻译: 在核电站中,核反应堆的第二操作循环中的热功率在第二操作周期之前的第一操作周期内从热功率上升至少一个操作周期。 在蒸汽系统中提取的蒸汽的比例相对于主蒸汽的流量被引入特定从高压汽轮机的中间点和出口抽出的给水加热器在第二操作 循环,从而在第二操作循环中使得从给水加热器排出的给水温度降低1℃至40℃。

    Operation method of nuclear power plant
    5.
    发明授权
    Operation method of nuclear power plant 有权
    核电厂运行方式

    公开(公告)号:US07614233B2

    公开(公告)日:2009-11-10

    申请号:US11340643

    申请日:2006-01-27

    IPC分类号: G21D5/00

    摘要: In a nuclear power plant, thermal power in a second operation cycle of a nuclear reactor is uprated from thermal power in a first operation cycle preceding the second operation cycle by at least one operation cycle. A proportion of steam extracted from a steam system and introduced to a feedwater heater, which is in particular extracted from an intermediate point and an outlet of a high pressure turbine, with respect to a flow rate of main steam, is reduced in the second operation cycle from that in the first operation cycle such that the temperature of feedwater discharged from the feedwater heater is lowered by 1° C. to 40° C. in the second operation cycle.

    摘要翻译: 在核电站中,核反应堆的第二操作循环中的热功率在第二操作周期之前的第一操作周期内从热功率上升至少一个操作周期。 在蒸汽系统中提取的蒸汽的比例相对于主蒸汽的流量被引入特定从高压汽轮机的中间点和出口抽出的给水加热器在第二操作 循环,从而在第二操作循环中使得从给水加热器排出的给水温度降低1℃至40℃。

    OPERATION METHOD OF NUCLEAR POWER PLANT
    7.
    发明申请
    OPERATION METHOD OF NUCLEAR POWER PLANT 有权
    核电厂的运行方法

    公开(公告)号:US20100170246A1

    公开(公告)日:2010-07-08

    申请号:US12574219

    申请日:2009-10-06

    IPC分类号: G21D5/00 F01K23/02

    摘要: In a nuclear power plant, thermal power in a second operation cycle of a nuclear reactor is uprated from thermal power in a first operation cycle preceding the second operation cycle by at least one operation cycle. A proportion of steam extracted from a steam system and introduced to a feedwater heater, which is in particular extracted from an intermediate point and an outlet of a high pressure turbine, with respect to a flow rate of main steam, is reduced in the second operation cycle from that in the first operation cycle such that the temperature of feedwater discharged from the feedwater heater is lowered by 1° C. to 40° C. in the second operation cycle.

    摘要翻译: 在核电站中,核反应堆的第二操作循环中的热功率在第二操作周期之前的第一操作周期内从热功率上升至少一个操作周期。 在蒸汽系统中提取的蒸汽的比例相对于主蒸汽的流量被引入特定从高压汽轮机的中间点和出口抽出的给水加热器在第二操作 循环,从而在第二操作循环中使得从给水加热器排出的给水温度降低1℃至40℃。