公开(公告)号:US12160101B1
公开(公告)日:2024-12-03
申请号:US18598582
申请日:2024-03-07
Applicant: 8ME NOVA, LLC
Inventor: Lukas Hansen , Gautham Ramesh , Philippe Garneau-Halliday , Kyle Monson , Brandon Carpenter , Rahul Mondal , Emily Arnold
IPC: H02J13/00
Abstract: A system for optimizing a network of power plants includes at least one memory storing a network model of a network of power plants and at least one processor. The network model includes a first power plant model of a first power plant including equipment models of power plant equipment of the first power plant, a second power plant model of a second power plant including equipment models of power plant equipment of the second power plant, and a plant relationship between the first power plant and the second power plant. The at least one processor is configured to receive a first input including an augmentation and replacement schedule for the second power plant, receive a second input modifying an attribute of a first equipment model of the first power plant model, and modify the schedule for the second power plant based on the second input and the plant relationship.
-
公开(公告)号:US12118629B2
公开(公告)日:2024-10-15
申请号:US18087364
申请日:2022-12-22
Applicant: 8ME NOVA, LLC
Inventor: Gautham Ramesh , Zeljko Gigio Sakota , Finbar Sheehy
CPC classification number: G06Q50/06 , H02J3/32 , H02J3/381 , H02J7/0048 , H02J2300/24 , H02J2300/40
Abstract: A system includes a renewable energy source (RES) that provides electrical energy and a first energy storage system (ESS) coupled to and configured to receive electrical energy from the RES, wherein the first ESS is configured to direct electrical energy to a source-sensitive destination. The system further includes a second ESS coupled to and configured to receive electrical energy from the RES and coupled to and configured to receive electrical energy from a non-renewable energy source to receive electrical energy, wherein the second ESS is configured to direct electrical energy to a non-source-sensitive destination.
-
公开(公告)号:US20240212069A1
公开(公告)日:2024-06-27
申请号:US18087364
申请日:2022-12-22
Applicant: 8ME NOVA, LLC
Inventor: Gautham Ramesh , Zeljko Gigio Sakota , Finbar Sheehy
CPC classification number: G06Q50/06 , H02J3/32 , H02J3/381 , H02J7/0048 , H02J2300/24 , H02J2300/40
Abstract: A system includes a renewable energy source (RES) that provides electrical energy and a first energy storage system (ESS) coupled to and configured to receive electrical energy from the RES, wherein the first ESS is configured to direct electrical energy to a source-sensitive destination. The system further includes a second ESS coupled to and configured to receive electrical energy from the RES and coupled to and configured to receive electrical energy from a non-renewable energy source to receive electrical energy, wherein the second ESS is configured to direct electrical energy to a non-source-sensitive destination.
-
公开(公告)号:US11949233B1
公开(公告)日:2024-04-02
申请号:US18470852
申请日:2023-09-20
Applicant: 8ME NOVA, LLC
Inventor: Elahesadat Naghib , Casey Olives , Jamie Link , Kip Larson
CPC classification number: H02J3/003 , H02J3/004 , H02J3/32 , H02J3/381 , H02J2203/20 , H02J2300/24
Abstract: A system for determining power flows in a power plant including an energy storage system (ESS) including an energy storage device and a power generation system comprising a power source includes at least one memory storing a power plant model. The power plant model includes an ESS model including an energy storage device model, a power generation system model, a load model of a load configured to receive power from the power plant, and system relationships between the ESS model, the power generation system model, and the load model. The system further includes at least one processor configured to receive input parameters for the load, determine a power flow rate at a point in the power plant or an energy storage level of the energy storage device at a first time step, and generate a record comprising an indication of the power flow rate or energy storage level.
-
公开(公告)号:US11949231B1
公开(公告)日:2024-04-02
申请号:US18370658
申请日:2023-09-20
Applicant: 8ME NOVA, LLC
Inventor: Lukas Hansen , Gautham Ramesh , Philippe Garneau-Halliday , Kyle Monson , Brandon Carpenter , Rahul Mondal , Emily Arnold
IPC: H02J13/00
CPC classification number: H02J13/00002 , H02J2203/20
Abstract: A system for optimizing a network of power plants includes at least one memory storing a network model of a network of power plants including a power plant model for each power plant, each power plant model including one or more equipment models of power plant equipment of a power plant, and plant relationships between the power plant models. The system further includes at least one processor configured to modify an attribute of a first equipment model included in a first power plant model of a first power plant, identify at least one plant relationship between the first power plant model and a second power plant model of a second power plant, determine an expected change in operation of the second power plant based on the modified attribute and the at least one plant relationship, and generate a record including an indication of the expected change.
-
6.
公开(公告)号:US11876399B1
公开(公告)日:2024-01-16
申请号:US18472770
申请日:2023-09-22
Applicant: 8ME NOVA, LLC
Inventor: Nadim Kanan , Lukas Hansen
CPC classification number: H02J7/342 , H02J3/32 , H02J7/0049 , H02J7/00712 , H02J2203/10 , H02J2300/20
Abstract: The present disclosure provides systems and methods for offsetting parasitic energy losses of a battery energy storage system (BESS). A method may include determining, by one or more processors of a renewable energy power plant coupled to an energy grid, a condition is satisfied; and responsive to the determination, adjusting, by the one or more processors, a state of a switch from a first state configured to couple a second BESS with a renewable energy source (RES) to a second state configured to couple the second BESS with the BESS. The RES configured to charge the T-BESS when the switch is in the first state and the T-BESS configured to send energy to the devices to satisfy energy requirements of the devices when the switch is in the second state.
-
公开(公告)号:US20230378754A1
公开(公告)日:2023-11-23
申请号:US18225025
申请日:2023-07-21
Applicant: 8ME NOVA, LLC
Inventor: Thomas Buttgenbach , Lukas Hansen , Philippe Garneau-Halliday , Emily Arnold , Stephanie Perry , Finbar Sheehy
IPC: H02J3/00 , H02S10/20 , H02S40/38 , G06Q10/04 , G06Q50/06 , H02S50/00 , H02J3/32 , G05B19/042 , H02J3/38
CPC classification number: H02J3/007 , H02S10/20 , H02S40/38 , G06Q10/04 , G06Q50/06 , H02J3/004 , H02S50/00 , H02J3/32 , G05B19/042 , H02J3/381 , H02J2300/24 , H02J2300/28 , G05B13/02
Abstract: A method for implementing power delivery of an integrated renewable energy source and energy storage system (RES-ESS) facility includes a renewable energy source (RES) and an energy storage system (ESS). The method comprises obtaining a first control rule configured to be used to control power distribution in the RES-ESS facility for a time slot, wherein the power distribution includes directing power from a renewable energy source (RES) to an electric grid and to an energy storage system (ESS) and power from the ESS to the electric grid; receiving a second control rule configured to be used to control the power distribution in the RES-ESS facility, wherein the second control rule was used to control the power distribution in the RES-ESS facility for the time slot; determining a difference in performance of the RES-ESS facility; and transmitting a record comprising an identification of the difference in performance.
-
公开(公告)号:US11824357B2
公开(公告)日:2023-11-21
申请号:US18118581
申请日:2023-03-07
Applicant: 8ME NOVA, LLC
Inventor: Thomas Buttgenbach , Finbar Sheehy , Alex Rozkin , Charlie Patton
CPC classification number: H02J3/003 , H02J3/004 , H02J3/381 , H02J2203/10 , H02J2300/24 , H02J2300/28
Abstract: A micro utility system. The micro utility system may include a portable container housing a plurality of pairs of rails on opposing interior faces of walls of the portable container and an energy storage system (ESS); a plurality of portable solar panel structures each comprising two or more solar panels coupled to each other at one end, each of the plurality of portable solar panel structures supported by a different pair of the plurality of pairs of rails; one or more charging port located on an exterior face of a first wall of the portable container and electrically connected to the ESS; and one or more discharging port located on the exterior face of the first wall or an exterior face of a second wall of the portable container and electrically connected to the ESS.
-
公开(公告)号:US20230369866A1
公开(公告)日:2023-11-16
申请号:US18119067
申请日:2023-03-08
Applicant: 8me Nova, LLC
Inventor: Thomas Buttgenbach
CPC classification number: H02J3/381 , H02J3/004 , H02J2300/28 , H02J2300/22 , H02J2203/10 , H02J2300/40
Abstract: A method described delivers power to a first load and a second load from networked power plants. The method may include receiving a power delivery profile for the first load, receiving a power delivery profile for a second load, determining a power output capability of a first renewable energy power plant (REPP), and determining a power output capability of a second REPP. The method may also include setting a power output for the first REPP and a power output for the second REPP based on the power delivery profile for the first and second loads and the power output capabilities of the first and second REPPs. The method may also include allocating a combined power output of the first and second REPPs to the first and second loads and delivering the allocated combined power output to the first and second loads.
-
公开(公告)号:US11757404B2
公开(公告)日:2023-09-12
申请号:US18120058
申请日:2023-03-10
Applicant: 8ME NOVA, LLC
Inventor: Lukas Hansen , Philippe Garneau-Halliday , Gautham Ramesh , Bora Akyol , Brandon Carpenter , Rahul Mondal
CPC classification number: H02S50/00 , H01M10/425 , H02J3/004 , H02J3/32 , H02J3/381 , H02J7/0071 , H02S10/12 , H02S40/38 , H01M2010/4271 , H02J2300/20 , H02J2300/24 , H02J2300/28
Abstract: A method includes generating a time-varying charge/discharge control signal for an electrical storage device, wherein generating the time-varying charge/discharge control signal comprises identifying a prioritization order of a stack of simultaneously operating control modes, the stack of simultaneously operating control modes including a staging mode and at least two additional control modes, each control mode of the stack comprising a plurality of control signal candidate values; identifying an intersection of one or more control signal candidate values from the plurality of control signal candidate values of each control mode of the stack according to the prioritization order; and determining, based on the prioritization order, at least one time-varying charge/discharge control signal for the electrical energy storage device from the intersection of control signal candidate values.
-
-
-
-
-
-
-
-
-