METHOD FOR FORMING A STEEP EMBANKMENT, SYSTEM FOR USE IN THE FORMATION OF THE STEEP EMBANKMENT AND SUCH STEEP EMBANKMENT
    11.
    发明申请
    METHOD FOR FORMING A STEEP EMBANKMENT, SYSTEM FOR USE IN THE FORMATION OF THE STEEP EMBANKMENT AND SUCH STEEP EMBANKMENT 审中-公开
    形成施工的方法,用于形成施工和这种施工的系统

    公开(公告)号:WO1997043489A1

    公开(公告)日:1997-11-20

    申请号:PCT/DK1997000209

    申请日:1997-05-07

    Inventor: BYGGROS A/S

    CPC classification number: E02D29/0241 E02D17/18 E02D29/0225

    Abstract: In the construction of a steep embankment a planar front grid (2) is used, said grid being positioned with a given inclination corresponding to the completed embankment, immediately adjacent the front of the completed embankment. At a point in the earth formation behind the completed embankment an anchor element (5) is placed, and between the front grid (2) and the anchor element (5) one or more fixed anchors braces (4a, 4b) are established to secure the front grid (2) in relation to the anchor element (5). Furthermore, one or more layers of geo-net (7) are preferably placed or inserted below or above the anchor element (5) and behind the front grid (2). Finally, the area behind the front grid (2) is filled up, whereby the anchor element (5) is covered to provide the earth formation in the completed embankment. In this method is used a universally applicable system comprising a planar front grid, an anchor element and a number of anchor braces or struts, said system being immediately adaptable to a given application.

    Abstract translation: 在建设一个陡峭的堤岸时,使用一个平面的前格栅(2),所述格栅以与完成的堤坝相对应的给定倾角定位,紧邻完成路堤的前部。 在完成的路堤后面的地层中的一个点处,放置锚定元件(5),并且在前格栅(2)和锚固元件(5)之间,建立一个或多个固定锚固支架(4a,4b)以固定 所述前格栅(2)相对于所述锚固元件(5)。 此外,地层网(7)的一层或多层优选地放置或插入锚固元件(5)的下方或上方,并且位于前格栅(2)的后方。 最后,填充了前格栅(2)后面的区域,由此锚固元件(5)被覆盖以在完成的路堤中提供地层。 在该方法中,使用包括平面前格栅,锚定元件和多个锚固支架或支柱的通用应用系统,所述系统可以立即适应给定应用。

    法丁張装置及び法丁張方法
    13.
    发明申请

    公开(公告)号:WO2018109838A1

    公开(公告)日:2018-06-21

    申请号:PCT/JP2016/087052

    申请日:2016-12-13

    Abstract: 【課題】部材の再利用を可能としながらも、設置作業が極めて容易な法丁張装置及び法丁張方法を提供する。 【解決手段】所定勾配の法面に沿うように斜貫板5の傾斜姿勢を調節する指標となる複数の勾配目盛線45を備えた勾配目盛部44と、前記斜貫板5の傾斜姿勢が前記勾配目盛線45の何れかに沿うように、前記斜貫板5を移動及び回動可能に支持する斜貫板支持機構46と、を備えて構成されている横貫板4を含む法丁張装置。

    SEALING SYSTEM FOR DAM WALLS
    14.
    发明申请
    SEALING SYSTEM FOR DAM WALLS 审中-公开
    大坝墙体密封系统

    公开(公告)号:WO2018014069A1

    公开(公告)日:2018-01-25

    申请号:PCT/AU2017/000152

    申请日:2017-07-19

    Abstract: A sealing system for tailings dam walls; said system including covering inward sloping walls of embankments forming a perimeter of said tailings dam with an impervious barrier; said impervious barrier in the form of a composite of at least two differentiated layers of material.

    Abstract translation:

    用于尾矿坝壁的密封系统; 所述系统包括覆盖堤坝的向内倾斜的壁,形成所述尾矿坝的周边的防渗屏障; 所述不透水屏障以至少两个不同层材料的复合物的形式存在。

    施工管理システム及び施工管理方法
    15.
    发明申请
    施工管理システム及び施工管理方法 审中-公开
    建筑管理体系与施工管理方法

    公开(公告)号:WO2016208276A1

    公开(公告)日:2016-12-29

    申请号:PCT/JP2016/063451

    申请日:2016-04-28

    Abstract: 施工管理システムは、施工現場の現況地形を示す現況地形データを取得する現況地形データ取得部と、施工現場の設計地形を示す設計地形データを取得する設計地形データ取得部と、現況地形データと設計地形データとを照合して、土砂の切土計画データ、及び土砂の盛土計画データを含む施工計画データを算出する施工計画データ算出部と、施工計画データを出力装置に出力する施工計画データ出力部と、を備える。施工計画データ出力部は、出力装置に、設計地形データ、切土計画データ、及び盛土計画データの少なくとも二つを並べて出力させる。

    Abstract translation: 施工管理系统具有:当前地形数据采集单元,用于获取表示施工现场当前地形的当前地形数据; 设计的地形数据获取单元,用于获取表示施工现场的设计地形的设计地形数据; 施工计划数据计算单元,用于通过将当前地形数据与所设计的地形数据进行对照来计算包括地面切割计划数据和土方填筑计划数据的施工计划数据; 以及用于将施工计划数据输出到输出装置的施工计划数据输出单元。 施工计划数据输出单元使得输出装置并排地输出设计的地形数据,切割计划数据和填充计划数据中的至少两个。

    RETAINING WALL SOIL REINFORCING CONNECTOR AND METHOD
    16.
    发明申请
    RETAINING WALL SOIL REINFORCING CONNECTOR AND METHOD 审中-公开
    保持墙土壤增强连接器和方法

    公开(公告)号:WO2011127349A3

    公开(公告)日:2012-01-26

    申请号:PCT/US2011031688

    申请日:2011-04-08

    Inventor: TAYLOR THOMAS P

    CPC classification number: E02D29/0233 E02D5/76 E02D29/0241

    Abstract: An apparatus and method of connecting an earthen formation to a concrete facing of a mechanically stabilized earth (MSE) structure. A one-piece connector having a stem and a tab, wherein the stem is connected to a soil reinforcing element embedded within the earthen formation and the tab is connected to a facing anchor attached to the concrete facing. The connection allows soil reinforcing mats to swivel in a horizontal plane, but also to shift vertically in reaction to MSE settling or thermal expansion/contraction of an MSE structure.

    Abstract translation: 将土层连接到机械稳定地球(MSE)结构的混凝土面的装置和方法。 一种具有杆和突片的连接器,其中所述杆连接到埋在所述土层内的土壤增强元件,并且所述翼片连接到附接到所述混凝土面对的面向锚固件。 该连接允许土壤增强垫在水平面上旋转,而且垂直移动以响应MSE结构的MSE沉降或热膨胀/收缩。

    COVER SYSTEM WITH GAS COLLECTION SYSTEM FOR WASTE SITES AND ENVIRONMENTAL CLOSURES
    17.
    发明申请
    COVER SYSTEM WITH GAS COLLECTION SYSTEM FOR WASTE SITES AND ENVIRONMENTAL CLOSURES 审中-公开
    用于废物场地和环境关闭的气体收集系统的封闭系统

    公开(公告)号:WO2011119205A2

    公开(公告)日:2011-09-29

    申请号:PCT/US2011000507

    申请日:2011-03-21

    CPC classification number: B09B1/004 Y02W30/32

    Abstract: A cover system is provided for waste sites and environmental closures, in which the cover system comprises a synthetic grass and an impermeable geomembrane that can be applied without the use of heavy earthwork equipment as temporary or final cover to control odors, erosion, gas migration and contaminate migration. The invention allows installation on very steep slopes and does not require the use of an extensive anchoring system to resist wind uplift or slope failure. A gas collection system is located under the cover system for the collection of gas produced by the waste sites.

    Abstract translation: 为废物场所和环境封闭提供了覆盖系统,其中覆盖系统包括合成草和不渗透土工膜,其可以在不使用重土工设备作为临时或最终覆盖物的情况下施加以控制气味,侵蚀,气体迁移和 污染迁移。 本发明允许安装在非常陡峭的斜坡上,并且不需要使用广泛的锚固系统来抵抗风抬升或斜坡破坏。 气体收集系统位于覆盖系统下面,用于收集废物产生的气体。

    IMPROVED SLOPE OF AN OPEN CUT MINE
    18.
    发明申请
    IMPROVED SLOPE OF AN OPEN CUT MINE 审中-公开
    改进开放矿山的坡度

    公开(公告)号:WO2011054035A1

    公开(公告)日:2011-05-12

    申请号:PCT/AU2010/001459

    申请日:2010-11-04

    Inventor: HAILE, Andrew

    CPC classification number: E21C41/26

    Abstract: This invention relates to open cut mines and in particular an improved slope to of an open cut mine. The slope includes a substantially vertical batter face (5) with a plurality of reinforcing members (10) spaced from a crest (7) of the batter face (5).

    Abstract translation: 本发明涉及开采矿,尤其涉及开采矿的改进斜率。 斜坡包括具有与面糊(5)的顶部(7)间隔开的多个加强构件(10)的基本垂直的面糊面(5)。

    盛土の変形抑制工法
    19.
    发明申请
    盛土の変形抑制工法 审中-公开
    抑制管理变形的方法

    公开(公告)号:WO2010131330A1

    公开(公告)日:2010-11-18

    申请号:PCT/JP2009/058847

    申请日:2009-05-12

    CPC classification number: E02D17/18 E02D3/00 E02D27/34

    Abstract: 【課題】液状化時にも補強効果を維持し、盛土の過大な変形を抑制することができ、しかもコストの低廉化が可能である。 【解決手段】基礎地盤1が地震時に液状化を起こす場合に盛土の変形を抑制する工法であり、基礎地盤上部の掘削面上に、平面状補強材2を非液状化材料3により挟み込み敷設し、非液状化材料3の上に、盛土4を施工する。また、基礎地盤1の上に、平面状補強材2を非液状化材料3により挟み込み敷設し盛土4の一部を構築し、 非液状化材料3の上に、盛土4を施工する。

    Abstract translation: 抑制路基变形的方法即使基础地面液化,也能够保持增强效果,抑制路堤的过度变形,能够以降低的成本进行。 当地基(1)在地震期间液化时,抑制堤坝变形的方法。 平地加强材料(2)放置在基础地面上部的挖掘表面上,以保持在非液化材料(3)中,然后在非液化的构件上构建路堤(4) 材料(3)。 或者,将平坦的增强材料(2)放置在基础地面(1)上以便保持在非液化材料(3)中,从而构成路堤(4)的一部分,然后将路堤(4) )构造在非液化材料(3)上。

Patent Agency Ranking