STEAM CYCLE, AND METHOD FOR OPERATING A STEAM CYCLE
    11.
    发明申请
    STEAM CYCLE, AND METHOD FOR OPERATING A STEAM CYCLE 审中-公开
    蒸汽循环和蒸汽循环运行方法

    公开(公告)号:US20170044935A1

    公开(公告)日:2017-02-16

    申请号:US15306545

    申请日:2015-04-16

    CPC classification number: F01K13/02 F01K7/22 F01K9/04

    Abstract: A steam cycle for a power station, and to a method for operating, in particular for starting, a steam cycle. The steam cycle has a high-pressure turbine, a condenser and a steam generator. The steam generator is connected to the high-pressure turbine via a first line. Live steam quick-closing valves and live steam regulating valves for supplying the high-pressure turbine are arranged in the direction of the steam flow between the steam generator and the high-pressure turbine. A starting line is arranged downstream of the high-pressure turbine in the direction of the steam flow, the starting line connecting a waste steam region downstream of the high-pressure turbine with the condenser. At least one regulator regulates a closing of a starting valve for sealing the starting line, and an opening of the live steam valve, depending on the rotational speed, a temperature and load state of the high-pressure turbine.

    Abstract translation: 用于电站的蒸汽循环,以及用于操作,特别是用于启动蒸汽循环的方法。 蒸汽循环具有高压涡轮机,冷凝器和蒸汽发生器。 蒸汽发生器通过第一线连接到高压涡轮。 用于供给高压汽轮机的活蒸汽快关阀和活蒸汽调节阀沿蒸汽发生器和高压汽轮机之间的蒸汽流动方向排列。 在高压涡轮机的下游,在蒸汽流的方向上设置起始线,起始线将高压涡轮机下游的废蒸汽区域与冷凝器连接。 至少一个调节器根据转速,高压汽轮机的温度和负载状态来调节用于密封起动线的起动阀的关闭和活蒸汽阀的打开。

    Steam cycle, and method for operating a steam cycle

    公开(公告)号:US10167742B2

    公开(公告)日:2019-01-01

    申请号:US15306545

    申请日:2015-04-16

    Abstract: A steam cycle for a power station, and to a method for operating, in particular for starting, a steam cycle. The steam cycle has a high-pressure turbine, a condenser and a steam generator. The steam generator is connected to the high-pressure turbine via a first line. Live steam quick-closing valves and live steam regulating valves for supplying the high-pressure turbine are arranged in the direction of the steam flow between the steam generator and the high-pressure turbine. A starting line is arranged downstream of the high-pressure turbine in the direction of the steam flow, the starting line connecting a waste steam region downstream of the high-pressure turbine with the condenser. At least one regulator regulates a closing of a starting valve for sealing the starting line, and an opening of the live steam valve, depending on the rotational speed, a temperature and load state of the high-pressure turbine.

    METHOD AND CONTROL DEVICE FOR SYNCHRONIZING A TURBINE WITH THE CURRENT NETWORK

    公开(公告)号:US20170237263A1

    公开(公告)日:2017-08-17

    申请号:US15519168

    申请日:2015-10-05

    CPC classification number: H02J3/40 F01D17/24 F01K13/02 G05B15/02 H02P9/04 H02P9/08

    Abstract: A method and associated control device for synchronizing a turbine with an alternating current network having a network frequency, having the following steps: A) accelerating the turbine up to a frequency in the range of the network frequency; B) sensing an angle difference between the turbine and the alternating current network; C) sensing a speed difference between the turbine and the alternating current network; D) accelerating or decelerating the turbine such that the turbine follows a desired trajectory, wherein the desired trajectory is a trajectory calculated in advance that indicates, in dependence on the angle difference, a desired speed difference that should be present such that a target angular position between the turbine and the alternating current network suitable for synchronous feed-in is achieved when the speed of the turbine and the speed of the alternating current network correspond.

    METHOD FOR OPERATING A COMBINED CYCLE POWER PLANT
    16.
    发明申请
    METHOD FOR OPERATING A COMBINED CYCLE POWER PLANT 审中-公开
    组合式循环电厂的运行方法

    公开(公告)号:US20160146060A1

    公开(公告)日:2016-05-26

    申请号:US14905412

    申请日:2014-07-03

    CPC classification number: F01K23/101 F01K7/24 F01K13/02 F22B1/1815 Y02E20/16

    Abstract: A method for operating a combined cycle power plant, according to which shortly before the planned start-up of a parked load, the steam turbine is lowered to a very low output, the gas turbine is then operated in parked load, and next the steam turbine is powered up to a parked output. The GT operating power can be the rated power of the gas turbine. The ST operating power can be the rated power of the steam turbine.

    Abstract translation: 一种用于操作联合循环发电厂的方法,根据该方法,在暂停的负载的计划启动之前不久,蒸汽轮机降低到非常低的输出,然后燃气轮机在停放的负载下运行,接下来是蒸汽 涡轮机供电到停放的输出。 GT运行功率可以是燃气轮机的额定功率。 ST工作功率可以是蒸汽轮机的额定功率。

    STEAM POWER PLANT HAVING A MULTI-STAGE STEAM TURBINE
    17.
    发明申请
    STEAM POWER PLANT HAVING A MULTI-STAGE STEAM TURBINE 审中-公开
    具有多级蒸汽涡轮机的蒸汽发电厂

    公开(公告)号:US20140150431A1

    公开(公告)日:2014-06-05

    申请号:US14176419

    申请日:2014-02-10

    Abstract: A steam power plant includes a multi-stage steam turbine including a rotor and a flow duct formed from a plurality of stages, a boiler, and a first cooling medium supply. The first cooling medium supply opens out into the flow duct of the steam turbine downstream of an intermediate stage. The rotor comprises a first component and a second component. The second component is arranged downstream of the first component as viewed in the flow direction. The intermediate stage is arranged downstream of the first component.

    Abstract translation: 蒸汽发电厂包括多级蒸汽轮机,其包括转子和由多级构成的流动管道,锅炉和第一冷却介质供应源。 第一冷却介质供应通向中间阶段下游的蒸汽轮机的流动管道。 转子包括第一部件和第二部件。 当从流动方向观察时,第二部件布置在第一部件的下游。 中间级布置在第一部件的下游。