公开(公告)号:US11739495B2
公开(公告)日:2023-08-29
申请号:US17588208
申请日:2022-01-28
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
CPC分类号: E02D35/005 , E01D19/02 , E02D3/12 , E02D37/00
摘要: Disclosed are a reinforcing and lifting method and a reinforcing and lifting structure for large-scale piers of high-speed rail. The method comprises: obliquely drilling grouting holes for a pile shoe body downward around the bridge pier cap, the hole bottom goes deep into a pile foundation side position close to the bottom end of the bridge pier pile foundation, grouting the hole bottom, and reinforcing the soil body between a plurality of pile foundations and around the pile foundations to form the pile shoe body; vertically drilling holes downward around the bridge pier cap to form a plurality of curtain holes at intervals, and grouting the curtain holes to form an enclosed curtain wall, the curtain wall and the pile shoe body form an inverted groove structure; obliquely drilling holes downward to form lifting holes, such that the bridge piers are gradually raised to a preset height.
-
公开(公告)号:US11840820B2
公开(公告)日:2023-12-12
申请号:US17549932
申请日:2021-12-14
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
CPC分类号: E02D35/005 , E02D37/00 , E02D2250/003 , E02D2300/0018
摘要: Disclosed is a method for strengthening and lifting a high-rise building that has a raft foundation, comprising: arranging a plurality of measuring points at intervals around the outer contour of a building, and determining the side to be lifted of the building according to the elevation of the measuring points; distributing a plurality of reinforcement grouting holes perpendicular to a raft foundation at intervals within the range of the raft foundation, and using pressure grouting in the reinforcement grouting holes to form a reinforcement under the raft foundation; laying downwardly inclined lifting holes on the outer side of the raft foundation at two ends close to the side to be lifted of the building; and performing simultaneous pressure grouting in the lifting holes to lift the side to be lifted of the building.
-
公开(公告)号:US20220154420A1
公开(公告)日:2022-05-19
申请号:US17588208
申请日:2022-01-28
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
摘要: Disclosed are a reinforcing and lifting method and a reinforcing and lifting structure for large-scale piers of high-speed rail. The method comprises: obliquely drilling grouting holes for a pile shoe body downward around the bridge pier cap, the hole bottom goes deep into a pile foundation side position close to the bottom end of the bridge pier pile foundation, grouting the hole bottom, and reinforcing the soil body between a plurality of pile foundations and around the pile foundations to form the pile shoe body; vertically drilling holes downward around the bridge pier cap to form a plurality of curtain holes at intervals, and grouting the curtain holes to form an enclosed curtain wall, the curtain wall and the pile shoe body form an inverted groove structure; obliquely drilling holes downward to form lifting holes, such that the bridge piers are gradually raised to a preset height.
-
公开(公告)号:US20220145575A1
公开(公告)日:2022-05-12
申请号:US17580782
申请日:2022-01-21
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
IPC分类号: E02D35/00
摘要: A high-rise building settling reinforcing and lifting correcting construction method, comprising: drilling holes vertically downward around a foundation slab of a building, forming multiple curtain wall holes sunk into foundation soil at intervals; injecting slurry into the curtain wall holes, slurry ranges meshing and overlapping with each other, forming a curtain wall, the curtain wall enclosing foundation soil under the foundation slab of the building, separating foundation soil inside and outside the range of the building; providing multiple vertical reinforcement slurry injection holes on the foundation slab and injecting slurry, fully reinforcing soil near the foundation slab, forming a reinforcement body; drilling a hole downward, forming a lifting hole, pressure-injecting slurry into a bottom part of the lifting hole, the foundation soil is continuously filled and compressed, creating a lifting force, and the building gradually rising to a determined lift height.
-
5.
公开(公告)号:US11746496B2
公开(公告)日:2023-09-05
申请号:US17582003
申请日:2022-01-24
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
CPC分类号: E02D35/005 , E02D3/12 , E02D27/44
摘要: The present application relates to a precise lifting method and a lifting and reinforcing structure for a plant equipment foundation. The method includes the construction steps of: forming a curtain wall: drilling downwards at two sides of the plant equipment to form curtain holes and grouting the curtain holes, in which the grouting areas overlap each other to form two parallel curtain walls; forming a reinforcing body: drilling grouting holes inclining downwards, grouting the grouting holes to form the reinforcing body attached to a lower surface of a baseplate of the plant equipment foundation among a bottom of the baseplate and two curtain walls; and lifting: drilling lifting holes obliquely downwards to below the bottom of the reinforcing body and between two curtain walls; and conducting pressure grouting to the bottom of the lifting holes and then backward grouting upwards layer by layer.
-
公开(公告)号:US11732434B2
公开(公告)日:2023-08-22
申请号:US17580782
申请日:2022-01-21
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
CPC分类号: E02D35/005 , E02D27/34
摘要: A high-rise building settling reinforcing and lifting correcting construction method, comprising: drilling holes vertically downward around a foundation slab of a building, forming multiple curtain wall holes sunk into foundation soil at intervals; injecting slurry into the curtain wall holes, slurry ranges meshing and overlapping with each other, forming a curtain wall, the curtain wall enclosing foundation soil under the foundation slab of the building, separating foundation soil inside and outside the range of the building; providing multiple vertical reinforcement slurry injection holes on the foundation slab and injecting slurry, fully reinforcing soil near the foundation slab, forming a reinforcement body; drilling a hole downward, forming a lifting hole, pressure-injecting slurry into a bottom part of the lifting hole, the foundation soil is continuously filled and compressed, creating a lifting force, and the building gradually rising to a determined lift height.
-
公开(公告)号:US11453992B2
公开(公告)日:2022-09-27
申请号:US17037730
申请日:2020-09-30
发明人: Xuedong Cui , Tengyue Cui , Jiguang Wu
摘要: Provided are a pile foundation bearing platform settlement, reinforcement, lift-up and leveling structure and a construction method thereof. The structure includes a bearing platform and a plurality of pile foundations, a weak soil reinforcement layer under the bearing platform and a pile tip bearing stratum. The weak soil reinforcement layer forms a plurality of first grouting holes, and the first grouting hole extends through the bearing platform and communicates with the outside. The first grouting hole is used to perform primary grouting in the weak soil reinforcement layer. The pile tip bearing stratum forms a plurality of second grouting holes, and the second grouting hole extends through the weak soil reinforcement layer and the bearing platform, and communicates with the outside. The second grouting hole is used to perform secondary grouting in the pile tip bearing stratum.
-
8.
公开(公告)号:US20220145576A1
公开(公告)日:2022-05-12
申请号:US17582003
申请日:2022-01-24
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
摘要: The present application relates to a precise lifting method and a lifting and reinforcing structure for a plant equipment foundation. The method includes the construction steps of: forming a curtain wall: drilling downwards at two sides of the plant equipment to form curtain holes and grouting the curtain holes, in which the grouting areas overlap each other to form two parallel curtain walls; forming a reinforcing body: drilling grouting holes inclining downwards, grouting the grouting holes to form the reinforcing body attached to a lower surface of a baseplate of the plant equipment foundation among a bottom of the baseplate and two curtain walls; and lifting: drilling lifting holes obliquely downwards to below the bottom of the reinforcing body and between two curtain walls; and conducting pressure grouting to the bottom of the lifting holes and then backward grouting upwards layer by layer.
-
公开(公告)号:US20220098819A1
公开(公告)日:2022-03-31
申请号:US17549932
申请日:2021-12-14
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
摘要: Disclosed is a method for strengthening and lifting a high-rise building that has a raft foundation, comprising: arranging a plurality of measuring points at intervals around the outer contour of a building, and determining the side to be lifted of the building according to the elevation of the measuring points; distributing a plurality of reinforcement grouting holes perpendicular to a raft foundation at intervals within the range of the raft foundation, and using pressure grouting in the reinforcement grouting holes to form a reinforcement under the raft foundation; laying downwardly inclined lifting holes on the outer side of the raft foundation at two ends close to the side to be lifted of the building; and performing simultaneous pressure grouting in the lifting holes to lift the side to be lifted of the building.
-
-
-
-
-
-
-
-