1.
公开(公告)号:US20240318400A1
公开(公告)日:2024-09-26
申请号:US18678047
申请日:2024-05-30
发明人: Tengyue CUI
CPC分类号: E02D35/005 , E02D1/08 , E02D3/12 , E02D2600/40
摘要: An engineering method for reinforcing and lifting a sunken foundation of a residential building includes stratigraphic structure, conducting a curtain reinforcement, reinforcing and strengthening a shallow layer, reinforcing a deep layer, steadily lifting an intermediate layer, and reinforcement supports of the composite foundation, the shallow layer reinforcement and strengthening adopts a progressive layered reinforcement process, the foundation slab of the building is reinforced with grouting to form the reinforcement body of an integral raft composite foundation. A support of the composite foundation similar to the pile foundation is constructed under four corners of the building and under the main load-bearing walls of the room. A structure supporting the upper load is formed through repeated retreating and progressive grouting.
-
公开(公告)号:US12043974B2
公开(公告)日:2024-07-23
申请号:US17299009
申请日:2019-10-17
发明人: Hans Reinhardt
摘要: The present invention relates to a special civil engineering machine, in particular a slurry wall cutter, comprising at least one rotating tool and a tool drive that is arranged within a housing of the special civil engineering machine and is sealed with respect to the environment by means of at least one bearing seal in the region of its shaft exit from the housing to the driven tool, characterized in that the bearing seal comprises at least two separate sealing elements, whose arrangement forms a sealing chamber located between the sealing elements, wherein a pressure compensation device is provided, which controls the chamber pressure in the sealing chamber in dependence on the ambient pressure of the special civil engineering machine.
-
3.
公开(公告)号:US20240229400A9
公开(公告)日:2024-07-11
申请号:US18492792
申请日:2023-10-24
发明人: Binhua Xu , Ning He , Yanbin Jiang , Zhangchun Wang , Zhikun Yan , Yanzhang Zhou , Guirong Zhang , Yajun Qian , Xinjie Zhan , Zhongliu Zhang , Bin He , Denghua Li , Yang Kong , Yuting Xie , Xiang Yin
CPC分类号: E02D3/12 , E02B11/00 , E02D5/385 , E02D2250/0007 , E02D2250/003 , E02D2300/0018 , E02D2300/0079 , E02D2300/0085
摘要: A method for reinforcing soft ground by post-grouting combined with pressurized vacuum preloading is proposed, by pre-burying prefabricated vertical drains and air-boosted pipes in granular material piles, and the air-boosted pipes are used as grouting pipes to reduce the number of times of piling, which not only improves the construction efficiency, but also reduces the structural disturbance of the soil and the influence of smear effect, thus reducing the impact on the radial permeability and the radial consolidation coefficients. The method does not use geotextile bags for granular materials, which can avoid the problem of forming a localized clogging area around the geotextile bags, and the method not only improves the efficiency of vacuum transfer in a pre-consolidation stage, but also improves the grouting effect in the later stage, effectively enhances the strength of soft soil and makes granular material piles and the surrounding soil form composite ground.
-
公开(公告)号:US20240191136A1
公开(公告)日:2024-06-13
申请号:US18553767
申请日:2022-04-27
申请人: GMCO Corporation
发明人: Bruce Juelfs
CPC分类号: C09K17/32 , C08K5/1545 , C08L97/005 , C09K3/22 , E01C21/00 , E02D3/12 , E02D2300/0045
摘要: A composition as described herein for treating an exposed area for dust control and soil erosion stabilization is provided, the composition comprising: (i) about 30 to about 80% dissolved biopolymer solution by volume; (ii) about 10 to about 20% dissolved carbohydrate solution by volume; (iii) about 0.02 to about 0.25% nonionic surfactant solution by volume; and (iv) water that makes up a remaining volume to 100% wherein the composition is effectively free from magnesium chloride and calcium chloride. In one aspect, the composition as described herein may be free, substantially free, or effectively free from oil-based and hydrophobic content. A method for using the composition to treat an exposed surface for dust control and soil erosion stabilization is also provided.
-
公开(公告)号:US20240093453A1
公开(公告)日:2024-03-21
申请号:US18038594
申请日:2021-11-29
发明人: Davide GRASSI , Giovanni SPAGNOLI
摘要: The present invention concerns a grout injection device (10) and a method for injecting grout into a longitudinal hole, e.g. a borehole. The grout injection device (10) comprises a hose (11) having at least three separate lines (12,13,14) defined in the interior of said hose (11); a packer system (16) arranged at one end (15) of said hose (11), said packer system comprising a chamber (17), said chamber (17) being provided with an inlet opening (18) into which said at least three lines (12,13,24) of said hose (11) lead and one or more discharge openings (22,23,24) for releasing fluid from said chamber (17) into the surrounding of the packer system; and a pump system (30) arranged at the opposite end (28) of said hose (11), configured to inject fluids into said at least three lines (12,13,14) of said hose (11).
-
公开(公告)号:US20230374375A1
公开(公告)日:2023-11-23
申请号:US18087930
申请日:2022-12-23
申请人: Rebecca Ayers
发明人: Rebecca Ayers
CPC分类号: C09K8/80 , B07B13/003 , B07B13/11 , E02D3/12 , E21B43/267 , E21B43/04 , Y10T428/2982
摘要: An aggregate processing assembly is provided. The processing assembly includes a separator assembly having a central member extending from a first end to a second end, the central member supporting at least one helical flight provided between the first and second ends, the helical flight having a width provided between a proximal end and a distal end. An assembly housing is provided around a portion of the separator assembly, the assembly housing includes a collection portion for receiving processed feed stock which exits the separator assembly radially away from the central member outward past the distal end, and the collection portion includes a first outlet. A second outlet is coupled to the separator assembly for receiving processed feed stock which exits the separator assembly at the second end of the at least one helical flight. A proppant, an aggregate, a system for processing feed stock to produce a proppant or aggregate, and a method of producing a proppant or aggregate is also provided.
-
公开(公告)号:US11774438B2
公开(公告)日:2023-10-03
申请号:US17096921
申请日:2020-11-12
申请人: Keller Holding GmbH
IPC分类号: G01N33/38 , B28C7/02 , B28C7/04 , E02D3/12 , G01F1/34 , G01K13/00 , G01N1/38 , G01N9/32 , G01N27/04 , G01N11/00 , G01N11/06
CPC分类号: G01N33/383 , B28C7/024 , B28C7/0418 , B28C7/0481 , E02D3/12 , G01F1/34 , G01K13/00 , G01N1/38 , G01N9/32 , G01N11/00 , G01N11/06 , G01N27/04 , E02D2250/003 , E02D2300/0018 , G01N2011/0046
摘要: The disclosure provides a measurement set-up for a return cement suspension, a construction site arrangement with a measurement set-up, and a method which can be carried out inexpensively, reliably, and easily.
-
8.
公开(公告)号:US11746496B2
公开(公告)日:2023-09-05
申请号:US17582003
申请日:2022-01-24
发明人: Xuedong Cui , Jiguang Wu , Tengyue Cui
CPC分类号: E02D35/005 , E02D3/12 , E02D27/44
摘要: The present application relates to a precise lifting method and a lifting and reinforcing structure for a plant equipment foundation. The method includes the construction steps of: forming a curtain wall: drilling downwards at two sides of the plant equipment to form curtain holes and grouting the curtain holes, in which the grouting areas overlap each other to form two parallel curtain walls; forming a reinforcing body: drilling grouting holes inclining downwards, grouting the grouting holes to form the reinforcing body attached to a lower surface of a baseplate of the plant equipment foundation among a bottom of the baseplate and two curtain walls; and lifting: drilling lifting holes obliquely downwards to below the bottom of the reinforcing body and between two curtain walls; and conducting pressure grouting to the bottom of the lifting holes and then backward grouting upwards layer by layer.
-
公开(公告)号:US11686061B2
公开(公告)日:2023-06-27
申请号:US17469389
申请日:2021-09-08
发明人: Steven M. Trout
CPC分类号: E02D3/12 , E02F3/9262 , E02D2250/003
摘要: An extraction/grouting device which includes a fluid conduit having a longitudinal extent along a longitudinal axis, a pivoting wand and at least one cutting nozzle. The nozzle being in fluid communication with the fluid conduit. The cutting nozzle being coupled to the pivoting wand that is pivotably extendable relative to the longitudinal axis.
-
10.
公开(公告)号:US20220341116A1
公开(公告)日:2022-10-27
申请号:US17725569
申请日:2022-04-21
申请人: Yuanqiang Cai , Jun Wang , Hongtao Fu , Shihu Gao , Bin Yang , Xiaoxiao Zhu , Rila Anda , Guohui Yuan
发明人: Yuanqiang Cai , Jun Wang , Hongtao Fu , Shihu Gao , Bin Yang , Xiaoxiao Zhu , Rila Anda , Guohui Yuan
摘要: A method for foundation consolidation combining vacuum preloading and geomembrane bag assembly loading, which comprises: digging a slurry pit, filling mud into the slurry pit and conducting vacuum preloading pumpdrainage for multiple times, laying the geomembrane bag assemblies above the soft slurry seam processed through vacuum preloading pumpdrainage inside the slurry pit to form a plurality of loading layers, and laying the geomembrane bag assemblies by piling geomembrane bags. In view of the engineering complexity and uneven settlement resulting from conventional vacuum preloading using slag loading, geomembrane bag for loading to overcome the adverse effects of slag loading. In the present invention, the drainage system and the geomembrane bag assemblies are laid out to fully leverage their perspective properties, so as to improve the transmission of vacuity in the whole soil mass, speed up the drainage rate, and increase the degree of consolidation.
-
-
-
-
-
-
-
-
-