公开(公告)号:US5324139A
公开(公告)日:1994-06-28
申请号:US19246
申请日:1993-02-18
申请人: Harald Wagner , Alfred Schulter , Helmut Pfeil , Otto Schubert
发明人: Harald Wagner , Alfred Schulter , Helmut Pfeil , Otto Schubert
CPC分类号: E21D9/0607 , E21D9/0609
摘要: A new combination of means and method steps is used in a method of constructing long tunnels with a lining, wherein excavation is effected with a tunnel boring machine (1) with a yielding shield mantle (4), building is effected continuously under the protection of the shield tail in a modular construction with tubbing stones of a special form complementing each other to form tubbing rings (15) while, until a new equilibrium of the rock formation is reached, occurring deformation forces are absorbed by the shield tail (4) and the tubbing rings which are yieldingly constructed to a limited degree, an outer seal of the tubes is provided and the gap between the excavation (2) and the tunnel tubes is filled with a material (22) which may be yielding to a limited extent to absorb long-time deformation forces. A tunnel construction made by the method, special forms of tubbing stones and new embodiments of drive means for the tunnel are disclosed.
摘要翻译: 一种新的组合方法和方法步骤用于构建具有衬里的长隧道的方法,其中采用具有屈服盾构地幔(4)的隧道掘进机(1)进行挖掘,建筑物在 屏蔽尾巴采用模块化结构,具有互相补充的特殊形式的石块,以形成桶形环(15),同时在达到岩层的新平衡之前,发生的变形力被盾尾(4)吸收,并且 提供了在有限程度上有力地构造的管形环,管的外部密封件,并且挖掘(2)和隧道管之间的间隙填充有材料(22),材料可能在有限的程度上屈服于 吸收长时间的变形力。 公开了通过该方法制造的隧道结构,特殊形式的滚石和用于隧道的驱动装置的新实施例。