1.
公开(公告)号:US20240013113A1
公开(公告)日:2024-01-11
申请号:US18266122
申请日:2022-09-08
Applicant: Samsung Engineering Co., Ltd.
Inventor: Byung Chul YOO , Hyeon Gi BAEK , Hyun Il LEE , Yong Duk PARK , Ki Yong JEONG , Jae Eun KIM , Syung Houn BAE
IPC: G06Q10/0631 , G06Q50/08
CPC classification number: G06Q10/06314 , G06Q10/06313 , G06Q10/06316 , G06Q50/08
Abstract: Disclosed is a method and system for automatic establishment of an optimal schedule for a construction project. The disclosed method of automatic establishment of an optimal schedule for a construction project is a computer-implemented method of automatic establishment of an optimal schedule for a construction project, the method including: providing project data, standardized schedule data, and characteristic data (S10); generating project schedule data by combining the project data, the standardized schedule data, and the characteristic data (S20); and deriving an optimal project schedule by processing the project schedule data through a scheduling optimization algorithm (S30).