Process and apparatus for installing a payload onto a subsea structure

    公开(公告)号:US11028663B1

    公开(公告)日:2021-06-08

    申请号:US16686996

    申请日:2019-11-18

    Abstract: A process for installing the payload onto a subsea structure has the steps of affixing an adapter spool on to the subsea structure, deploying a plurality of winches in spaced relation to the subsea structure, connecting an end of a plurality of slings received on the plurality of sheaves to a plurality of winches, connecting an opposite end of the plurality of slings to the payload, lowering the payload in a direction toward the subsea structure, actuating the plurality of winches so as to draw the payload downwardly into a position on the subsea structure, and locking the payload onto the subsea structure. The adapter spool has a collar with a plurality of sheaves extending outwardly therefrom. The payload can be a capping stack and the subsea structure can be a blowout preventer.

    Process for remediating hydrates from subsea flowlines

    公开(公告)号:US10273785B2

    公开(公告)日:2019-04-30

    申请号:US15808255

    申请日:2017-11-09

    Abstract: A process for removing hydrate formations from a flowline includes connecting a manifold to the flowline, passing an inert gas across a pair of inlets of the manifold so as to create a reduced pressure across the pair of inlets that is less than a pressure of a fluid in the flowline, opening a valve between the pair of inlets and the flowline so as to expose the pressurized fluid in the flowline to the reduced pressure across the pair of inlets, disassociating hydrates in the flowline by exposure to the reduced pressure across the pair of inlets, and flowing the fluid and the disassociated hydrates from the flowline into the outlet of the manifold and outwardly of the manifold through at least one of the pair of inlets.

    Process for non-vertical installation and removal of a subsea structure

    公开(公告)号:US10781670B1

    公开(公告)日:2020-09-22

    申请号:US16598662

    申请日:2019-10-10

    Abstract: A process for installing or removing a subsea structure in a non-vertical manner at a well includes securing a plurality of barges together in a linear formation in which one of the plurality of barges has a downline extending therefrom, connecting an end of the barges to a primary vessel, moving the primary vessel such that one of the barges is positioned over a target at or adjacent to the well, connecting a plurality of secondary vessels by plurality of mooring lines to an opposite end of the barges, tensioning the mooring line so as to fix the opposite end of the barges, positioning a deployment vessel away from the barges, deploying an ROV, manipulating the ROV so as to connect the subsea structure to the downline, and moving the downline and the subsea structure toward or away from the well.

Patent Agency Ranking