公开(公告)号:US20190383142A1
公开(公告)日:2019-12-19
申请号:US16479215
申请日:2018-01-13
Applicant: Yubin Wang
Inventor: Yubin Wang
Abstract: Disclosed is a tunneling apparatus for use in a pipe jacking method, the tunneling apparatus including an excavating apparatus (1), a head front-end track (2), a central track (3) and a rear apparatus (4), wherein the excavating apparatus (1) is composed of a transmission apparatus (1-1) and a cutter (5), the transmission apparatus (1-1) being composed of a driving apparatus (1-1-1) and a sprocket (1-1-3); during construction, the chain cutter (5) for excavating rock and earth runs on the head front-end track (2) and the central track (3), and the shape of a head excavation face is the same as that of the cross section of a tube section (6); the rear apparatus (4) comprises a jacking apparatus (4-1), mounted in a construction well; the front end of the central track (3) is connected to the head front-end track (2), the tail end of the central track (3) is connected to the rear apparatus (4), and during construction, the driving apparatus (1-1-1) drives the chain cutter (5), so that the chain cutter (5) runs along the tracks; and a cutter on the head front-end track (2) excavates the ring-shaped rock and earth in a projection part of the cross section of the tube section (6). In a work well, an operating platform is constructed, and the impact on the surrounding environment is low. The head of a first tube section (6) is an excavating face of the excavating apparatus (1), excavated rock and earth are driven along with the chain cutter (5) into the work well, the tube section (6) is ejected into position and then the rock and earth are cleared in the tube section (6), construction is simple, quality is good, the construction period is short, and costs are low.
-
公开(公告)号:US20190330984A1
公开(公告)日:2019-10-31
申请号:US16410625
申请日:2019-05-13
Applicant: Tongji University
Inventor: Xiongyao XIE , Biao ZHOU , Yunxiang ZHOU , Hui QIN , Yifan CHEN
Abstract: The present invention relates to a loaded-to-frame detection equipment for backfill grouting of a shield tunnel, including an automatic loaded-to-frame transmission apparatus, a ground penetrating radar, and an intelligent backfill grouting processing and analysis software. The equipment is integrated by using software and hardware, and can implement real-time visual detection of a backfill grouting layer in a shield construction process. The loaded-to-frame automatic transmission apparatus mainly includes a track, a synchronous belt, a transmission mechanism, a servo machine, and a drive and reducer; and a new air-coupled radar detection apparatus is carried on the loaded-to-frame automatic transmission apparatus and is installed on a shield frame. With the shield performs tunneling, circular detection on a grouting body of the shield and visual layered display of the grouting body are implemented.
-
公开(公告)号:US10428638B2
公开(公告)日:2019-10-01
申请号:US15465798
申请日:2017-03-22
Applicant: Atlas Copco Drilling Solutions LLC
Inventor: Peter D. Miller
Abstract: A system and method for drilling a borehole using a drilling rig having a rotary drill bit includes monitoring one or more drilling parameters; determining whether the one or more monitored drilling parameters are within predetermined specifications for one or more of the monitored drill parameters; and, executing an exception control procedure for control of a drilling parameter. The exception control procedure receives an input sensor value associated with a drilling parameter and applies feedback control to establish a scaled error value that is used to compute a setting value for the drilling parameter. The drilling parameters controlled may include the rotation speed of the drill bit, the feed rate of the drill bit, the weight-on-bit, or rotation torque during retraction of the drill bit. A computer-readable database of specifications of drill bits may be provided as a part of the system.
-
公开(公告)号:US10392819B2
公开(公告)日:2019-08-27
申请号:US15746278
申请日:2016-07-13
Applicant: YOOGU E&C Co., Ltd. , Woon Sik Hwang
Inventor: Woon Sik Hwang
Abstract: The present invention relates to a grouting apparatus. In detail, the present invention provides a grouting apparatus which injects a reinforcing material into an object in which an injection hole into which the reinforcing material is injected is formed, the grouting apparatus including: a pumping unit which pumps the reinforcing material to be injected into the object; an injection pipe which has one side connected to the pumping unit, and the other side inserted into the injection hole, and injects the reinforcing material conveyed by the pumping unit into the object; a vibration generating unit which generates vibration; and a vibration wire which has one end coupled to the vibration generating unit, and the other end extending along the injection pipe and coupled to a tip of the injection pipe, and transmits the vibration generated by the vibration generating unit to the injection pipe.
-
公开(公告)号:US10370967B2
公开(公告)日:2019-08-06
申请号:US15509635
申请日:2015-09-07
Applicant: MEKOROT WATER COMPANY, LTD.
Inventor: Ben Ami Sorek , Orel Markovich
Abstract: An integrated jacking pipe comprising a concrete jacking envelope integrally-formed with and encircling a metal pipe, wherein said metal pipe comprises a spigot protruding from said concrete jacking envelope and a bell whose diameter is larger than a diameter of said spigot.
-
公开(公告)号:US10208595B2
公开(公告)日:2019-02-19
申请号:US15105772
申请日:2013-12-17
Applicant: SANDVIK MINING AND CONSTRUCTION OY
Inventor: Anssi Kouhia , Jussi Puura
Abstract: An arrangement and method of utilizing rock drilling information in a mine whereby drill holes are drilled in a surrounding rock material by a first mining vehicle. During drilling measuring data is produced and is inputted to a monitoring device for analyzing procedures. The monitoring device produces rock condition data of the rock material being drilled. The produced rock condition data is then implemented in a second mining vehicle.
-
公开(公告)号:US09903391B2
公开(公告)日:2018-02-27
申请号:US13811987
申请日:2011-08-05
Applicant: Eduard Heindl
Inventor: Eduard Heindl
CPC classification number: F15B1/045 , E21D9/00 , E21D9/006 , F03B17/00 , F03G3/00 , H02J15/003 , Y02E10/20 , Y02E60/17
Abstract: A system for storing potential energy includes a hydraulic cylinder, a mass to be lifted, and a sealing ring at the edge of the mass to be lifted. The mass to be lifted is a solid rock mass in the form of a cut-out solid rock. The hydraulic cylinder is formed by the cavity between surrounding rocks and the cut-out solid rock. The cavity is sealed with respect to the surrounding rocks by the sealing ring. A method for producing such a system is also provided.
-
38.
公开(公告)号:US20180010452A1
公开(公告)日:2018-01-11
申请号:US15632291
申请日:2017-06-23
Inventor: Weijiang CHU , Chunsheng ZHANG , Jing HOU , Yong ZHOU , Pingzhi CHEN
Abstract: The present invention relates to a surrounding rock pretreatment method for a TBM (tunnel boring machine) passing through a round tunnel section with high rock-burst risk. A technical solution of the present invention is as follows: the surrounding rock pretreatment method includes the following steps: 1. determining a pretreatment area, wherein an area in which a clear spacing between a to-be-constructed tunnel and an adjacent existing tunnel in a TBM tunneling direction is less than 2 times that of a tunnel diameter of the TBM to-be-constructed tunnel is the pretreatment area: 2. performing controlled blasting; 3. injecting high pressure water, and selecting part of blast holes I to perform cyclic water injection pressurizing; and 4, performing normal tunneling by the TBM.
-
公开(公告)号:US20170342834A1
公开(公告)日:2017-11-30
申请号:US15538143
申请日:2015-12-22
Applicant: JAMES CRAWFORD THOMSON
Inventor: JAMES CRAWFORD THOMSON
IPC: E21D9/00 , E01C1/00 , E02D29/045
CPC classification number: E21D9/005 , E01C1/002 , E02D29/045 , E21D9/03
Abstract: A method and apparatus for forming a tunnel structure at a relatively shallow depth from the surface, which tunnel can be used as a replacement or additional transport route to an existing transport route (2) which is already formed on the surface. The method comprises the steps of forming two spaced apart access tunnels, installing piles (15), installing slide tracks (17) in each of the tunnels, removing a part of the tunnels (hatched portion) to expose the tracks, introducing units (22) comprising side walls portions (26, 28) and a roof section (30) by moving the units along the tracks while excavating the soil in which the tunnel is to be formed is in advance of the leading edge of the units.
-
40.
公开(公告)号:US20170122103A1
公开(公告)日:2017-05-04
申请号:US15302043
申请日:2015-04-02
Applicant: MONTANUNIVERSITÄT LEOBEN , HERRENKNECHT AKTIENGESELLSCHAFT , B+ G BETONTECHNOLOGIE MATERIALBEWIRTSCHAFTUNG AG
Inventor: Stefan Barwart , Robert Galler
Abstract: A mining tool (100) for a drill head (150) of a tunnel boring machine (180) for mining in rock (102), wherein the mining tool (100) has a roller cutter fastening device (104), mountable on the drill head (150), for accommodating and mounting a rotatable roller cutter (106), the roller cutter (106) for mining in rock (102) is accommodated or in particular can be interchangeably accommodated rotatably in the roller cutter fastening device (104), and a sensor arrangement (112) for detecting a mechanical load of the mining tool (100), in particular of the roller cutter (106), wherein the sensor arrangement (112) is formed at least partially in the roller cutter fastening device (104) and/or on the sleeve (177) mounted on the roller cutter (106) with at least one load-sensitive element (108) mounted thereon.
-
-
-
-
-
-
-
-
-