公开(公告)号:US11486804B1
公开(公告)日:2022-11-01
申请号:US17846945
申请日:2022-06-22
Applicant: QINGDAO UNIVERSITY OF TECHNOLOGY , Qingdao Green Technology Geotechnical Engineering Co., Ltd. , China State Construction Zhongxin Construction Engineering Co., Ltd. Shandong Branch , Shandong Luqiao Group Co., Ltd., Jinan, China , Zhongji Jiurui Geotechnical Engineering Co., Ltd.
Inventor: Yonghong Wang , Mingyi Zhang , Jun Wang , Bo Han , Jiangbin Wu , Chuantong Zhang , Xiang Fang , Yishun Jiang , Yuning Ge , Qijun Zhang , Weihui Tian , Yan Li , Xun Zhu , Baochang Zhang , Guodong Shao
Abstract: Provided are a device for simulating a full-scale pile-sinking process of a static pressure pile by air bag preloading and a test method thereof. The device comprises a frame, a beam, a hydraulic jack, a model box, a model pile, a first sand layer, an undisturbed soil mass, a second sand layer, a rubber pad, a forcing air bag, a counter-force steel plate, a model box top cover, a forcing pipe, a pressure relief pipe, a steel casing and a control system. The first sand layer, the undisturbed soil mass, the second sand layer, the rubber pad, the forcing air bag and the counter-force steel plate are laid in the model box in sequence; and the steel casing passes through the model box top cover, the counter-force steel plate, the forcing air bag and the rubber pad in sequence and then reaches a bottom portion of the second sand layer.
-
2.
公开(公告)号:US20220145574A1
公开(公告)日:2022-05-12
申请号:US17581912
申请日:2022-01-22
Applicant: QINGDAO UNIVERSITY OF TECHNOLOGY , Qingdao Green Technology Geotechnical Engineering Co., Ltd. , Chongqing University
Inventor: Yonghong WANG , Shujuan YANG , Wengang ZHANG , Jiangbin WU , Jian HUANG , Qianqing ZHANG , Qijun ZHANG , Lei SU , Bingxiang YUAN , Jifei CUI , Xiang FANG , Chuantong ZHANG , Guodong SHAO , Zhaolong LI , Lin CUI
Abstract: A system and method for monitoring an earth pressure and displacement of a miniature steel pipe pile body. Sensor installation holes are drilled at predetermined positions outside the steel pipe pile body and sensor metal protective shell with a thickness slightly lower than that of the XY-TY02A resistance-type miniature earth pressure gauge is welded on the steel pipe pile body. The XY-TY02A resistance-type miniature earth pressure gauges are stuck on the steel pipe pile body. The transmission line of the XY-TY02A resistance-type miniature earth pressure gauges passes through the sensor installation holes and are connected to data acquisition system. The reflective sheet base is welded at the preset position of the miniature steel pipe pile and the reflective sheet is attached to the reflective sheet base to realize displacement monitoring.
-
公开(公告)号:US20220145568A1
公开(公告)日:2022-05-12
申请号:US17581911
申请日:2022-01-22
Applicant: QINGDAO UNIVERSITY OF TECHNOLOGY , Qingdao Green Technology Geotechnical Engineering Co., Ltd. , Zhongqing Jian'an Construction Group Co., Ltd.
Inventor: Yonghong WANG , Bo HAN , Jian HUANG , Qijun ZHANG , Jiangbin WU , Wengang ZHANG , Peiyuan LIN , Junning XIANG , Jun YAN , Bin WANG , Wenzhuo LIU , Chengyue JIA , Xiang FANG , Xin WANG , Zuodong LIANG
Abstract: A concrete inside interface processing structure for secant pile construction, including secant concrete pile, formed plain concrete pile, rotary jet grouting piles, steel mesh sheet, ribbed steel bar, Y-shaped connecting piece, reinforced concrete pile, and U-shaped connecting piece; drilled holes are arranged at intervals along axis of the formed plain concrete pile; the ribbed steel bar is anchored in each drilled hole; the steel mesh sheet is formed by connecting longitudinal bars and transverse bars, and driven into a soil body between the formed plain concrete piles; the concrete layer is formed by spraying concrete on the steel mesh sheet; the reinforced concrete pile is cast at outside of the formed plain concrete pile, and tangent to the formed plain concrete pile, and interlocked with the rotary jet grouting piles; the rotary jet grouting piles are tangent to the formed plain concrete pile or secant concrete pile.
-
公开(公告)号:US11635284B1
公开(公告)日:2023-04-25
申请号:US17846951
申请日:2022-06-22
Applicant: QINGDAO UNIVERSITY OF TECHNOLOGY , Qingdao Green Technology Geotechnical Engineering Co., Ltd. , Zhongji JiuRui Geotechnical Engineering Co., Ltd. , Shandong Luqiao Group Co., Ltd., Jinan, China , China State Construction Zhongxin Construction Engineering Co., Ltd. Shandong Branch
Inventor: Yonghong Wang , Mingyi Zhang , Xiang Fang , Bo Han , Qijun Zhang , Yishun Jiang , Shiqiang Li , Dazhong Xu , Jun Wang , Chuantong Zhang , Yuning Ge , Yamei Zhang , Weihui Tian , Ziguang Jia , Xiaoning Liu
Abstract: Provided are a testing apparatus for a pile end settlement of a rock-socketed driven PHC tube pile and an installation method thereof. The testing apparatus comprises a PHC tube pile, two measuring tubes, a cross pile tip, a pile tip steel plate, a fixer fixed in the PHC tube pile, a perforated steel plate located at a pile top of the PHC tube pile and a jack pressed on the perforated steel plate. The two measuring tubes are symmetrically arranged, the fixer is provided with two first measuring tube outlet holes, and the two measuring tubes respectively pass through the first measuring tube outlet holes of the fixer; and the perforated steel plate is also provided with two second measuring tube outlet holes, and the two measuring tubes respectively pass through the second measuring tube outlet holes of the perforated steel plate.
(FIG. 1)-
公开(公告)号:US11384502B2
公开(公告)日:2022-07-12
申请号:US17581911
申请日:2022-01-22
Applicant: QINGDAO UNIVERSITY OF TECHNOLOGY , Qingdao Green Technology Geotechnical Engineering Co., Ltd. , Zhongqing Jian'an Construction Group Co., Ltd.
Inventor: Yonghong Wang , Bo Han , Jian Huang , Qijun Zhang , Jiangbin Wu , Wengang Zhang , Peiyuan Lin , Junning Xiang , Jun Yan , Bin Wang , Wenzhuo Liu , Chengyue Jia , Xiang Fang , Xin Wang , Zuodong Liang
Abstract: A concrete inside interface processing structure for secant pile construction, including secant concrete pile, formed plain concrete pile, rotary jet grouting piles, steel mesh sheet, ribbed steel bar, Y-shaped connecting piece, reinforced concrete pile, and U-shaped connecting piece; drilled holes are arranged at intervals along axis of the formed plain concrete pile; the ribbed steel bar is anchored in each drilled hole; the steel mesh sheet is formed by connecting longitudinal bars and transverse bars, and driven into a soil body between the formed plain concrete piles; the concrete layer is formed by spraying concrete on the steel mesh sheet; the reinforced concrete pile is cast at outside of the formed plain concrete pile, and tangent to the formed plain concrete pile, and interlocked with the rotary jet grouting piles; the rotary jet grouting piles are tangent to the formed plain concrete pile or secant concrete pile.
-
-
-
-