Methods and apparatus to generate schedules to execute functions in a process control system
    3.
    发明授权
    Methods and apparatus to generate schedules to execute functions in a process control system 失效
    用于生成调度以执行过程控制系统中的功能的方法和装置

    公开(公告)号:US07761171B2

    公开(公告)日:2010-07-20

    申请号:US11537303

    申请日:2006-09-29

    IPC分类号: G05B15/02

    摘要: An example apparatus includes a first interface configured to identify a first function associated with a process control routine. The example apparatus also includes a sub-schedule generator configured to generate a first sub-schedule associated with a first time period. The first sub-schedule indicates a first execution time at which the first function is to be executed. The example apparatus also includes a schedule generator configured to form a schedule associated with a second time period based on two instances of the first sub-schedule. The schedule indicates the first execution time and a second execution time at which the first function is to be executed.

    摘要翻译: 示例性设备包括被配置为识别与过程控制例程相关联的第一功能的第一接口。 该示例设备还包括被配置为生成与第一时间段相关联的第一子时间表的子时间表发生器。 第一子时间表指示要执行第一功能的第一执行时间。 该示例设备还包括调度生成器,其被配置为基于第一子调度的两个实例来形成与第二时间段相关联的调度。 该调度表示第一执行时间和执行第一功能的第二执行时间。

    Automatic configuration of synchronous block execution for control modules run in fieldbus networks
    5.
    发明授权
    Automatic configuration of synchronous block execution for control modules run in fieldbus networks 有权
    在现场总线网络中运行的控制模块的自动配置同步块执行

    公开(公告)号:US08005553B2

    公开(公告)日:2011-08-23

    申请号:US11968087

    申请日:2007-12-31

    IPC分类号: G05B11/01

    摘要: A method or apparatus automatically configures a control module for synchronous execution on a Fieldbus segment of a process control network by determining if all of the critical function blocks of a particular control module can be assigned to FOUNDATION® Fieldbus field devices or to the I/O device associated with a particular Fieldbus segment. If so, the method or apparatus automatically assigns the function blocks of the control module, which would otherwise be scheduled to execute in a controller, to the I/O device for the Fieldbus segment. This technique enables all of the critical or necessary function blocks within the control module to execute in one macrocycle of the Fieldbus segment, thereby executing synchronously on a Fieldbus segment. This operation, in turn, increases the overall execution rate of the control module with respect to control modules that have function blocks split between a controller and field devices on a Fieldbus segment, which has been the traditional manner of configuring control modules implemented using devices on a Fieldbus segment.

    摘要翻译: 一种方法或装置通过确定特定控制模块的所有关键功能块是否可以分配给FOUNDATION®现场总线现场设备或I / O来自动配置用于在过程控制网络的现场总线段上同步执行的控制模块 与特定现场总线段相关联的设备。 如果是这样,则该方法或设备将将控制模块的功能块(否则将被调度为在控制器中执行)自动分配给现场总线段的I / O设备。 该技术使得控制模块内的所有关键或必需功能块能够在现场总线段的一个宏环中执行,从而在现场总线段上同步执行。 这种操作反过来又增加了控制模块相对于在现场总线段上的控制器和现场设备之间分开的功能块的控制模块的总执行率,这是传统的配置使用设备实现的控制模块的方式 现场总线部分。

    Automatic Configuration of Synchronous Block Execution for Control Modules Run in Fieldbus Networks
    7.
    发明申请
    Automatic Configuration of Synchronous Block Execution for Control Modules Run in Fieldbus Networks 有权
    自动配置在现场总线网络中运行的控制模块的同步块执行

    公开(公告)号:US20080249641A1

    公开(公告)日:2008-10-09

    申请号:US11968087

    申请日:2007-12-31

    IPC分类号: G05B15/02

    摘要: A method or apparatus automatically configures a control module for synchronous execution on a Fieldbus segment of a process control network by determining if all of the critical function blocks of a particular control module can be assigned to FOUNDATION® Fieldbus field devices or to the I/O device associated with a particular Fieldbus segment. If so, the method or apparatus automatically assigns the function blocks of the control module, which would otherwise be scheduled to execute in a controller, to the I/O device for the Fieldbus segment. This technique enables all of the critical or necessary function blocks within the control module to execute in one macrocycle of the Fieldbus segment, thereby executing synchronously on a Fieldbus segment. This operation, in turn, increases the overall execution rate of the control module with respect to control modules that have function blocks split between a controller and field devices on a Fieldbus segment, which has been the traditional manner of configuring control modules implemented using devices on a Fieldbus segment.

    摘要翻译: 一种方法或装置通过确定特定控制模块的所有关键功能块是否可以被分配给现场总线现场设备或I(I))来自动配置用于在过程控制网络的现场总线段上同步执行的控制模块 / O设备与特定现场总线段相关联。 如果是这样,则该方法或设备将将控制模块的功能块(否则将被调度为在控制器中执行)自动分配给现场总线段的I / O设备。 该技术使得控制模块内的所有关键或必需功能块能够在现场总线段的一个宏环中执行,从而在现场总线段上同步执行。 这种操作反过来又增加了控制模块相对于在现场总线段上的控制器和现场设备之间分开的功能块的控制模块的总执行率,这是传统的配置使用设备实现的控制模块的方式 现场总线部分。

    METHODS AND APPARATUS TO GENERATE SCHEDULES TO EXECUTE FUNCTIONS IN A PROCESS CONTROL SYSTEM
    8.
    发明申请
    METHODS AND APPARATUS TO GENERATE SCHEDULES TO EXECUTE FUNCTIONS IN A PROCESS CONTROL SYSTEM 失效
    生成在过程控制系统中执行功能的时间表的方法和装置

    公开(公告)号:US20080082193A1

    公开(公告)日:2008-04-03

    申请号:US11537303

    申请日:2006-09-29

    IPC分类号: G06F19/00

    摘要: Example methods and apparatus to generate schedules to execute functions in a process control system are disclosed. A disclosed example apparatus includes a first interface configured to identify a first function associated with a process control routine. The example apparatus also includes a sub-schedule generator configured to generate a first sub-schedule associated with a first time period. The first sub-schedule indicates a first execution time at which the first function is to be executed. The example apparatus also includes a schedule generator configured to form a schedule associated with a second time period based on two instances of the first sub-schedule. The schedule indicates the first execution time and a second execution time at which the first function is to be executed.