1.
公开(公告)号:US06920365B2
公开(公告)日:2005-07-19
申请号:US10740258
申请日:2003-12-18
Applicant: Jen-Lin Chao , Chao-Hsien Lin , Chen-Wei Hsu , Chin-Yung Chang
Inventor: Jen-Lin Chao , Chao-Hsien Lin , Chen-Wei Hsu , Chin-Yung Chang
CPC classification number: G06Q10/06
Abstract: A system for planning and controlling a pull-in request of an order with demanded capacity in a production system. A plan engine is programmed to receive a pull-in request for the order, release original demanded capacity, reserve a capacity for the pull-in order, and generate a fixed production schedule for the pull-in order based on a capacity model that considers a plurality of capacity vectors in the production system. A production schedule monitor and evaluation module determines whether the relevant current pull-in order conforms to the fixed production schedule and whether to adjust the fixed production schedule when the relevant current pull-in order deviates from the fixed production schedule.
Abstract translation: 一种用于规划和控制生产系统中具有需求能力的订单的拉入请求的系统。 计划引擎被编程为接收订单的拉入请求,释放原始请求的容量,为拉入订单预留容量,并且基于考虑的容量模型生成用于拉入订单的固定生产计划 生产系统中的多个容量向量。 生产进度监视和评估模块确定相关的当前引入顺序是否符合固定生产计划,以及当相关的当前引入顺序偏离固定生产计划时是否调整固定生产计划。
-
2.
公开(公告)号:US20050149899A1
公开(公告)日:2005-07-07
申请号:US10750750
申请日:2004-01-02
Applicant: Jen-Lin Chao , Chin Yung Chang
Inventor: Jen-Lin Chao , Chin Yung Chang
CPC classification number: G06F17/50 , G03F7/70425 , G03F7/70433 , G06F2217/84
Abstract: A system and method for MPW shuttle service. The system includes at least a first MPW shuttle reserving for a first group of device designs, a second MPW shuttle reserving for a second group of device designs, and a checking unit. The checking unit determines whether mask data for the first group has been provided by a cut off date for the first MPW shuttle, and exchanges a first target device design from the first group with a second target device design from the second group if the mask data of the first target device design has not been provided and that of the second target device design has been provided by the cut off date.
Abstract translation: 一种用于MPW穿梭服务的系统和方法。 该系统包括至少保留用于第一组设备设计的第一MPW梭,为第二组设备设计保留的第二MPW梭,以及检查单元。 检查单元确定是否已经为第一MPW穿梭机的截止日期提供了第一组的掩模数据,并且如果掩模数据,则从第一组与第二组的第二目标设备设计交换第一目标设备设计 的第一个目标设备设计尚未提供,第二个目标设备设计的截止日期已经提供。
-
3.
公开(公告)号:US07130707B2
公开(公告)日:2006-10-31
申请号:US10739843
申请日:2003-12-18
Applicant: Jen-Lin Chao , Chen-Wei Hsu , Chin-Yung Chang , Chiang-Chou Lo , Wei-Chuan Huang , Cheng-Hsi Wen
Inventor: Jen-Lin Chao , Chen-Wei Hsu , Chin-Yung Chang , Chiang-Chou Lo , Wei-Chuan Huang , Cheng-Hsi Wen
IPC: G06F19/00
CPC classification number: G06Q10/00 , G05B19/41865 , G05B2219/32086 , Y02P90/20
Abstract: A customer-orientated manufacturing planning and controlling system. An order management module is programmed to receive an order for a product and reserve a capacity for the order based on a capacity model that considers a plurality of capacity vectors in a production system. A plan engine generates a fixed production schedule for the order based on the capacity model. A priority management engine provides a priority for the order. A production schedule monitor and evaluation module determines whether the order in process conforms to the fixed production schedule by statistical process control (SPC) and whether to adjust the fixed production schedule and to adjust the priority based on a dynamic achievement model of historical fixed production schedules, based on historical production information in a production database storing production information of the production system.
Abstract translation: 以客户为导向的制造规划和控制系统。 订单管理模块被编程为接收产品的订单并且基于在生产系统中考虑多个容量向量的容量模型来保留订单的容量。 计划引擎根据容量模型生成订单的固定生产计划。 优先级管理引擎为订单提供优先级。 生产进度监视和评估模块通过统计过程控制(SPC)确定进程中的订单是否符合固定生产计划,以及是否根据历史固定生产计划的动态成果模型调整固定生产计划并调整优先级 基于存储生产系统生产信息的生产数据库中的历史生产信息。
-
4.
公开(公告)号:US07073160B2
公开(公告)日:2006-07-04
申请号:US10750750
申请日:2004-01-02
Applicant: Jen-Lin Chao , Chin Yung Chang
Inventor: Jen-Lin Chao , Chin Yung Chang
CPC classification number: G06F17/50 , G03F7/70425 , G03F7/70433 , G06F2217/84
Abstract: A system and method for MPW shuttle service. The system includes at least a first MPW shuttle reserving for a first group of device designs, a second MPW shuttle reserving for a second group of device designs, and a checking unit. The checking unit determines whether mask data for the first group has been provided by a cut off date for the first MPW shuttle, and exchanges a first target device design from the first group with a second target device design from the second group if the mask data of the first target device design has not been provided and that of the second target device design has been provided by the cut off date.
Abstract translation: 一种用于MPW穿梭服务的系统和方法。 该系统包括至少保留用于第一组设备设计的第一MPW梭,为第二组设备设计保留的第二MPW梭,以及检查单元。 检查单元确定是否已经为第一MPW穿梭机的截止日期提供了第一组的掩模数据,并且如果掩模数据,则从第一组与第二组的第二目标设备设计交换第一目标设备设计 的第一个目标设备设计尚未提供,第二个目标设备设计的截止日期已经提供。
-
公开(公告)号:US07031795B2
公开(公告)日:2006-04-18
申请号:US10797824
申请日:2004-03-10
Applicant: Jen-Lin Chao , Chin-Yung Chang
Inventor: Jen-Lin Chao , Chin-Yung Chang
IPC: G06F19/00
CPC classification number: G06Q10/06
Abstract: A system and method of coinsurance wafer management. The system includes at least one production line and an order management unit. The production line processes a MPW shuttle including original wafers and coinsurance wafers with a common fabrication process before metal layering, processes the original wafers with different metal layering fabrication processes according to a metal layering technology of each device design of the MPW shuttle, and withholds the coinsurance wafers without further fabrication. The order management unit receives a request for a designated device design before a cutoff date, and the production line releases and processes coinsurance wafers with the metal layering fabrication process corresponding to the designated device design when the request is received.
Abstract translation: 一种共同保证晶片管理的系统和方法。 该系统包括至少一条生产线和订单管理单元。 该生产线在金属分层之前通过普通的制造工艺处理包括原始晶片和共晶保护晶片的MPW穿梭,根据MPW穿梭机的每种设备设计的金属分层技术处理具有不同金属分层制造工艺的原始晶片,并且保留 共同保证的晶片无需进一步制造。 订单管理单元在截止日期之前接收到指定的设备设计的请求,并且当接收到请求时,生产线释放并处理具有与指定的设备设计相对应的金属分层制造过程的共同保险晶片。
-
公开(公告)号:US20050203658A1
公开(公告)日:2005-09-15
申请号:US10797824
申请日:2004-03-10
Applicant: Jen-Lin Chao , Chin-Yung Chang
Inventor: Jen-Lin Chao , Chin-Yung Chang
IPC: G06F19/00
CPC classification number: G06Q10/06
Abstract: A system and method of coinsurance wafer management. The system includes at least one production line and an order management unit. The production line processes a MPW shuttle including original wafers and coinsurance wafers with a common fabrication process before metal layering, processes the original wafers with different metal layering fabrication processes according to a metal layering technology of each device design of the MPW shuttle, and withholds the coinsurance wafers without further fabrication. The order management unit receives a request for a designated device design before a cutoff date, and the production line releases and processes coinsurance wafers with the metal layering fabrication process corresponding to the designated device design when the request is received.
Abstract translation: 一种共同保证晶片管理的系统和方法。 该系统包括至少一条生产线和订单管理单元。 该生产线在金属分层之前通过普通的制造工艺处理包括原始晶片和共晶保护晶片的MPW穿梭,根据MPW穿梭机的每种设备设计的金属分层技术处理具有不同金属分层制造工艺的原始晶片,并且保留 共同保证的晶片无需进一步制造。 订单管理单元在截止日期之前接收到指定的设备设计的请求,并且当接收到请求时,生产线释放并处理具有与指定的设备设计相对应的金属分层制造过程的共同保险晶片。
-
公开(公告)号:US07103435B2
公开(公告)日:2006-09-05
申请号:US10677569
申请日:2003-10-02
Applicant: Jen-Lin Chao , Chin-Yung Chang , Wei-Kuo Yen
Inventor: Jen-Lin Chao , Chin-Yung Chang , Wei-Kuo Yen
IPC: G05B19/418 , G06F19/00
CPC classification number: G06Q10/06 , G06Q10/06312
Abstract: A system and method for control factor management for a work-in-process (WIP) in a production system. A plan engine is programmed to receive an order for a product, reserve a capacity for the order based on a capacity model that considers a plurality of capacity vectors, and generate a plan for the WIP of the order according to a control factor. A control factor management module adjusts the control factor of the plan engine according to a current value of the control factor in the production system, a target value of the control factor, and a priority of the WIP. Preferably, a control factor matrix of the product is provided in the control factor management module as a function of the current value of the control factor in the production system, the target value of the control factor, the priority of the WIP, and a target date of the order.
Abstract translation: 用于生产系统中的在制品(WIP)的控制因素管理的系统和方法。 计划引擎被编程为接收产品的订单,基于考虑多个容量向量的容量模型来保留订单的容量,并且根据控制因素生成用于订单的WIP的计划。 控制因素管理模块根据生产系统中的控制因素的当前值,控制因素的目标值以及WIP的优先级来调整计划引擎的控制因素。 优选地,控制因子管理模块中的控制因子矩阵作为生产系统中的控制因素的当前值,控制因子的目标值,WIP的优先级和目标值 订单日期
-
8.
公开(公告)号:US20050137733A1
公开(公告)日:2005-06-23
申请号:US10740258
申请日:2003-12-18
Applicant: Jen-Lin Chao , Chao-Hsien Lin , Chen-Wei Hsu , Chin-Yung Chang
Inventor: Jen-Lin Chao , Chao-Hsien Lin , Chen-Wei Hsu , Chin-Yung Chang
CPC classification number: G06Q10/06
Abstract: A system for planning and controlling a pull-in request of an order with demanded capacity in a production system. A plan engine is programmed to receive a pull-in request for the order, release original demanded capacity, reserve a capacity for the pull-in order, and generate a fixed production schedule for the pull-in order based on a capacity model that considers a plurality of capacity vectors in the production system. A production schedule monitor and evaluation module determines whether the relevant current pull-in order conforms to the fixed production schedule and whether to adjust the fixed production schedule when the relevant current pull-in order deviates from the fixed production schedule.
Abstract translation: 一种用于规划和控制生产系统中具有需求能力的订单的拉入请求的系统。 计划引擎被编程为接收订单的拉入请求,释放原始请求容量,为拉入订单预留容量,并且基于考虑到的容量模型生成用于拉入订单的固定生产计划 生产系统中的多个容量向量。 生产进度监视和评估模块确定相关的当前引入顺序是否符合固定生产计划,以及当相关的当前引入顺序偏离固定生产计划时是否调整固定生产计划。
-
9.
公开(公告)号:US20050137732A1
公开(公告)日:2005-06-23
申请号:US10739843
申请日:2003-12-18
Applicant: Jen-Lin Chao , Chen-Wei Hsu , Chin-Yung Chang , Chiang-Chou Lo , Wei-Chuan Huang , Cheng-Hsi Wen
Inventor: Jen-Lin Chao , Chen-Wei Hsu , Chin-Yung Chang , Chiang-Chou Lo , Wei-Chuan Huang , Cheng-Hsi Wen
IPC: G05B19/418 , G06F19/00 , G06Q10/00
CPC classification number: G06Q10/00 , G05B19/41865 , G05B2219/32086 , Y02P90/20
Abstract: A customer-orientated manufacturing planning and controlling system. An order management module is programmed to receive an order for a product and reserve a capacity for the order based on a capacity model that considers a plurality of capacity vectors in a production system. A plan engine generates a fixed production schedule for the order based on the capacity model. A priority management engine provides a priority for the order. A production schedule monitor and evaluation module determines whether the order in process conforms to the fixed production schedule by statistical process control (SPC) and whether to adjust the fixed production schedule and to adjust the priority based on a dynamic achievement model of historical fixed production schedules, based on historical production information in a production database storing production information of the production system.
Abstract translation: 以客户为导向的制造规划和控制系统。 订单管理模块被编程为接收产品的订单并且基于在生产系统中考虑多个容量向量的容量模型来保留订单的容量。 计划引擎根据容量模型生成订单的固定生产计划。 优先级管理引擎为订单提供优先级。 生产进度监视和评估模块通过统计过程控制(SPC)确定进程中的订单是否符合固定生产计划,以及是否根据历史固定生产计划的动态成果模型调整固定生产计划并调整优先级 基于存储生产系统的生产信息的生产数据库中的历史生产信息。
-
公开(公告)号:US20050075747A1
公开(公告)日:2005-04-07
申请号:US10677569
申请日:2003-10-02
Applicant: Jen-Lin Chao , Chin-Yung Chang , Wei-Kuo Yen
Inventor: Jen-Lin Chao , Chin-Yung Chang , Wei-Kuo Yen
CPC classification number: G06Q10/06 , G06Q10/06312
Abstract: A system and method for control factor management for a work-in-process (WIP) in a production system. A plan engine is programmed to receive an order for a product, reserve a capacity for the order based on a capacity model that considers a plurality of capacity vectors, and generate a plan for the WIP of the order according to a control factor. A control factor management module adjusts the control factor of the plan engine according to a current value of the control factor in the production system, a target value of the control factor, and a priority of the WIP. Preferably, a control factor matrix of the product is provided in the control factor management module as a function of the current value of the control factor in the production system, the target value of the control factor, the priority of the WIP, and a target date of the order.
Abstract translation: 用于生产系统中的在制品(WIP)的控制因素管理的系统和方法。 计划引擎被编程为接收产品的订单,基于考虑多个容量向量的容量模型来保留订单的容量,并且根据控制因素生成用于订单的WIP的计划。 控制因素管理模块根据生产系统中的控制因素的当前值,控制因素的目标值以及WIP的优先级来调整计划引擎的控制因素。 优选地,控制因子管理模块中的控制因子矩阵作为生产系统中的控制因素的当前值,控制因子的目标值,WIP的优先级和目标值 订单日期
-
-
-
-
-
-
-
-
-