Mining Method Without Coal Pillars With Roof-Cutting And Roadway Retaining

    公开(公告)号:US20230258083A1

    公开(公告)日:2023-08-17

    申请号:US17922128

    申请日:2021-04-30

    IPC分类号: E21C41/18 E21F1/00 E21F16/00

    CPC分类号: E21C41/18 E21F1/00 E21F16/00

    摘要: The present disclosure relates to the technical field of coal mining, and in particular, to a mining method without coal pillars with roof-cutting and roadway retaining, comprising: constructing a gas drainage roadway and eliminating outbursts in a working face transport gate area and a working face track gate area on opposite sides of a first mining working face; constructing the working face track gate, the working face transport gate, a first process roadway and a second process roadway, one end of the working face track gate is communicated with an air return roadway, the other end is communicated with the gas drainage roadway by the first process roadway, one end of the working face track gate is communicated with the air return roadway, the other end is communicated with the gas drainage roadway by the second process roadway; stoping the working face, forming an roadway retaining section, the roadway retaining section is communicated with the gas drainage roadway by the first process roadway and the second process roadway, forming a ventilation system. Make full use of the existing gas drainage roadway to meet the roadway layout requirements using the 110 construction method, increasing the use function of the roadway and increasing the reuse rate of the roadway, reducing the roadway engineering quantity before production, shortening the construction period and reduce the cost.

    Method for coal mining without reserving coal pillar and tunneling roadway in whole mining area

    公开(公告)号:US11578598B2

    公开(公告)日:2023-02-14

    申请号:US17597481

    申请日:2019-07-22

    IPC分类号: E21C41/00 E21C41/18 E21D9/14

    摘要: A coal mining method is provided without coal-pillar leaving and without laneway excavation in a full mining area. The coal mining method includes drilling a main shaft, an auxiliary shaft and a return air shaft from a ground to a coal mining layer; by a coal mining machine, forming a first mining face with a first direction as an advance direction; by the coal mining machine, cutting out a first haulageway and a first return airway while cutting the coal wall at the first mining face, and preserving the first haulageway and the first return airway. In this method, the first haulageway and the first return airway are located on two sides of the first mining face, the first haulageway is in communication with both of the main and auxiliary shafts, and the first return airway is in communication with the return air shaft.

    METHOD FOR COAL MINING WITHOUT RESERVING COAL PILLAR AND TUNNELING ROADWAY IN WHOLE MINING AREA

    公开(公告)号:US20220251953A1

    公开(公告)日:2022-08-11

    申请号:US17597481

    申请日:2019-07-22

    IPC分类号: E21C41/18 E21D9/14

    摘要: A coal mining method is provided without coal-pillar leaving and without laneway excavation in a full mining area. The coal mining method includes drilling a main shaft, an auxiliary shaft and a return air shaft from a ground to a coal mining layer; by a coal mining machine, forming a first mining face with a first direction as an advance direction; by the coal mining machine, cutting out a first haulageway and a first return airway while cutting the coal wall at the first mining face, and preserving the first haulageway and the first return airway. In this method, the first haulageway and the first return airway are located on two sides of the first mining face, the first haulageway is in communication with both of the main and auxiliary shafts, and the first return airway is in communication with the return air shaft.

    DESIGN METHOD FOR MINE WITHOUT LEAVING COAL PILLAR AND WITHOUT ROADWAY TUNNELING

    公开(公告)号:US20220251952A1

    公开(公告)日:2022-08-11

    申请号:US17597480

    申请日:2019-07-22

    IPC分类号: E21C41/18 E21D9/14

    摘要: A pit designing method is provided without coal-pillar leaving and laneway excavation. The method includes drilling a main shaft and an auxiliary shaft from a ground to a coal bed and exploiting in the coal bed first and second connection laneways. The first connection laneway is in communication with the main shaft, and the second connection laneway is in communication with the auxiliary shaft. The method further includes communicating the first and second connection laneways, and using a communication part between the first connection laneway and the second connection laneway as a first open-off cut; and by using a direction of the first open-off cut further away from the connecting line connecting the main shaft and the auxiliary shaft as a first direction, and exploiting by cutting a coal wall in the first direction using a coal mining machine.

    SYNERGISTIC MINING METHOD FOR UNDERGROUND MINING, SEPARATION AND FILLING FOR A CLOSE DISTANCE COAL SEAM GROUP

    公开(公告)号:US20210404337A1

    公开(公告)日:2021-12-30

    申请号:US16616603

    申请日:2018-11-02

    摘要: A synergistic mining method for underground mining, separation and filling for a close distance coal seam group is applicable to the mining engineering field. Full-mechanized caving mining is carried out for a close distance coal seam group, an underground coal gangue separation system and a filling face are designed according to the yield of gangue in the production process; the gangue produced in the mining process is transported centrally into an underground coal gangue separation chamber, and the separated gangue is transported to the filling face for filling and mining; the gangue produced at the filling face is transported back to the filling face for backfilling after underground washing separation. The method separates nearby and filling at selected locations, reduces the damage and disturbance to the underground rock mass that may be caused by a conventional mining method, and solves problems in treatment of strong dynamic pressure in advance.

    ZERO-GANGUE-DISCHARGE SHORT-WALL FACE PILLAR-FREE MINING METHOD

    公开(公告)号:US20210310356A1

    公开(公告)日:2021-10-07

    申请号:US16319033

    申请日:2018-05-23

    IPC分类号: E21F15/00 E21C41/18

    摘要: The present invention discloses a zero-gangue-discharge short-wall face pillar-free mining method, which is applicable to zero-gangue-discharge disposal in the mining operation in a mine shaft. A short-wall face is arranged in a selected area near a mine shaft according to the actual conditions of the mine shaft, the short-wall face is mined in a fully mining and fully back-filling mode, the gangues produced at other mining faces of the mine shaft are filled into the short-wall face, the short-wall face is supported with anchor rods along the edge of the filling face and the solid coal side to form an entry, and the entry is utilized to mine an adjacent working face. The method in the present invention mainly displaces the coal mass with gangues and thereby maximizes the utilization of the resources; in addition, the method can fully control the roof and realize mining without damage to the rock formation. Therefore, the method is of great value for wide application.