公开(公告)号:US20200256031A1
公开(公告)日:2020-08-13
申请号:US16858744
申请日:2020-04-27
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructrue Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Peng Zhao , Yanhui Pan , Xianfeng Zhao , Yingli Wang
摘要: A thin-slotting lifting synchronous grouting device and its usage method are provided, The device includes a hollow force-bearing column through which a feeding pipe passes; wherein: left and right cutting plates are respectively fixedly arranged on each side of the hollow force-bearing column; a left connecting plate is fixedly arranged on an outside of the left cutting plate; a right guiding column is fixedly arranged on an outside of the right cutting plate; center lines of the left connecting plate, the right guiding column and the hollow force-bearing column are in a same plane; a top end of to the feeding pipe is connected to a grouting device, and a bottom end is connected to a spraying device; a spraying nozzle of the spraying device stretches out along the hollow force-bearing column; and a lower end of the hollow force-bearing column is connected with a disposable conical head.
-
2.
公开(公告)号:US11585467B2
公开(公告)日:2023-02-21
申请号:US16871029
申请日:2020-05-10
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Peng Zhao , Yanhui Pan , Bin Li , Hang He
摘要: Trenchless methods for forming a curved hole channel with a steel sleeve and pipeline lifting are provided, including steps of: (T1) drilling a straight hole channel, and inserting the steel sleeve into the straight hole channel; (T2) inserting a guiding pipe into the steel sleeve, and determining a bending direction of a hole channel to be formed; and (T3) inserting a flexible steel-wire pipe into the guiding pipe, and punching to form the curved hole channel. With applying the creative trenchless method for forming the curved hole channel, a specially-made grouting pipe is accurately inserted to a bottom of a subsiding pipeline section, so that a polymer material is conveniently injected to a bottom of a disease position. Though utilizing an expansion force generated by the polymer material, the subsiding pipeline section is uplifted, so as to realize trenchless repairing.
-
公开(公告)号:US11346487B2
公开(公告)日:2022-05-31
申请号:US16871044
申请日:2020-05-11
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Peng Zhao , Yanhui Pan , Bin Li , Hang He
IPC分类号: F16L55/1645 , F16L55/18
摘要: A support tool for leakage repair of an inspection well includes: a curved loading plate having multiple grouting holes thereon, a telescopic adjustment device, and a base; wherein: one end of the telescopic adjustment device is connected to an inner side face of the curved loading plate, and the other end of the telescopic adjustment device is connected to the base; the telescopic adjustment device adjusts a distance between the curved loading plate and the base. The support tool is firstly hoisted at a leakage position of the inspection well; then a telescopic length of the telescopic adjustment device is adjusted, so that the curved loading plate and the base are in a close contact with opposite sides of the inspection well wall; and a grouting system is used to inject a double-slurry quick-setting repair material into a grouting pipe on the curved loading plate for plugging leakage.
-
公开(公告)号:US11149399B2
公开(公告)日:2021-10-19
申请号:US16858723
申请日:2020-04-27
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Peng Zhao , Yanhui Pan , Xianfeng Zhao , Yingli Wang
摘要: A track-type shotcrete integrated system includes: a proportioner working bin, a storage bin, a power bin, and load-bearing legs, wherein bottom sections of the load-bearing legs are equipped with a track chassis for moving, and the track chassis is electrically connected to a track controller; the storage bin contains a storage tank I and a storage tank II for storing different raw materials; a feed pump I is installed on a top of the storage tank I, and a feed pump II is installed on a top of the storage tank II; inlet pipes of the feed pump I and the feed pump II insert into the storage tank I and storage tank II respectively, and outlet pipes of the feed pump I and the feed pump II are connected to a feed pipe I and a feed pipe II respectively.
-
公开(公告)号:US11104612B2
公开(公告)日:2021-08-31
申请号:US16416199
申请日:2019-05-18
发明人: Fuming Wang , Hongyuan Fang , Lei Wang , Peng Zhao , Yanhui Pan
IPC分类号: C04B26/16 , C04B22/16 , C04B24/26 , C04B103/14 , C04B103/40 , C04B111/00 , C04B111/70
摘要: The present invention provides a rapid-hardening underground pipeline grouting repair polymer and a preparing method thereof for underground pipes. The rapid-hardening underground pipeline grouting repair polymer comprises the base resin and the hardener, weight ratio of which is 2:1-1:1. The base resin comprises 50 to 160 parts by weight of an isocyanate; 20 to 100 parts of a chlorophosphate mixture with a density over 1400 kg/m3; a parts by weight ratio of the isocyanate and chlorophosphate is 1:1-4:1. The hardener comprises 30 to 60 parts by weight of a chlorophosphate mixture with a density over 1400 kg/m3, 5 to 15 parts of a propyl formate, a methyl propionate or a mixture of a propyl formate and a methyl propionate, 15 to 55 parts of a polyol, 1 to 3 parts of a surfactant, 2 to 6 parts of a catalyst, 0 to 0.5 parts of water and 0 to 1 parts of a colorant.
-
公开(公告)号:US20200248551A1
公开(公告)日:2020-08-06
申请号:US16856057
申请日:2020-04-23
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Yanhui Pan , Peng Zhao , Chengchao Guo
IPC分类号: E21D9/00
摘要: A construction method of a rectangular working well includes steps of: (I) designing functional requirements for the rectangular working well; (II) constructing a caisson of an enclosing structure of the rectangular working well; (III) constructing an edge protector; (IV) excavating earthwork of the rectangular working well; (V) forming a back cover for the rectangular working well, and pre-embedding a sliding track, a pull ring and a back wall anchor; (VI) installing a ladder for entering the rectangular working well; (VII) preventing joint leakage; (VIII) installing a water-proof pressure plate at an entrance of the preset pipe jacking hole; (IX) constructing the sliding back wall; (X) lifting the sandwich concrete slab wall at a top of the preset pipe jacking hole; and (XI) performing pipe jacking. The structure system constructed by the present invention has many advantages such as clear function, safety, quickness, and flexible design.
-
公开(公告)号:US11473713B2
公开(公告)日:2022-10-18
申请号:US16858731
申请日:2020-04-27
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Peng Zhao , Yanhui Pan , Bin Li , Hang He
IPC分类号: F16L55/163 , F16L55/165 , F16L55/134 , F16L55/1645 , F16L9/08 , E03F3/06
摘要: A trenchless integrative repair method includes steps of: S1, pre-casting steel rings according to an internal diameter of a defect pipeline, and forming grouting holes in the steel rings; S2, loading the steel rings to a defect position inside the pipeline, and fitting the steel rings to an internal wall of the pipeline to form reinforcing rings; S3, selecting a number of the grouting holes according to subsidence distribution; drilling a hole in the pipeline to reach a subsidence position and inserting a grouting pipe; steadily grouting the subsidence position with a polymer grouting system, and observing a lift condition of the pipeline; removing the grouting pipe after the pipeline is lifted to a predetermined level; and S4, pulling a lining pipe into the pipeline, and fitting the lining pipe to the steel rings and pipeline walls adjacent to the steel rings; curing the lining pipe.
-
公开(公告)号:US11149400B2
公开(公告)日:2021-10-19
申请号:US16858744
申请日:2020-04-27
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Peng Zhao , Yanhui Pan , Xianfeng Zhao , Yingli Wang
摘要: A thin-slotting lifting synchronous grouting device and its usage method are provided. The device includes a hollow force-bearing column through which a feeding pipe passes; wherein: left and right cutting plates are respectively fixedly arranged on each side of the hollow force-bearing column; a left connecting plate is fixedly arranged on an outside of the left cutting plate; a right guiding column is fixedly arranged on an outside of the right cutting plate; center lines of the left connecting plate, the right guiding column and the hollow force-bearing column are in a same plane; a top end of to the feeding pipe is connected to a grouting device, and a bottom end is connected to a spraying device; a spraying nozzle of the spraying device stretches out along the hollow force-bearing column; and a lower end of the hollow force-bearing column is connected with a disposable conical head.
-
公开(公告)号:US11143027B2
公开(公告)日:2021-10-12
申请号:US16856057
申请日:2020-04-23
申请人: Infrastructure Renewal Institute of Southern China , WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd.
发明人: Fuming Wang , Hongyuan Fang , Yanhui Pan , Peng Zhao , Chengchao Guo
IPC分类号: E21D5/01 , E02D23/08 , F16L55/165 , F16L55/18 , E21D9/00
摘要: A construction method of a rectangular working well includes steps of: (I) designing functional requirements for the rectangular working well; (II) constructing a caisson of an enclosing structure of the rectangular working well; (III) constructing an edge protector; (IV) excavating earthwork of the rectangular working well; (V) forming a bottom cover for the rectangular working well, and pre-embedding a sliding track, a pull ring and a back wall anchor; (VI) installing a ladder for entering the rectangular working well; (VII) preventing joint leakage; (VIII) installing a water-proof pressure plate at an entrance of the preset pipe jacking hole; (IX) constructing the sliding back wall; (X) lifting the sandwich concrete slab wall at a top of the preset pipe jacking hole; and (XI) performing pipe jacking. The structure system constructed by the present invention has many advantages such as clear function, safety, quickness, and flexible design.
-
公开(公告)号:US20190270672A1
公开(公告)日:2019-09-05
申请号:US16416199
申请日:2019-05-18
发明人: Fuming Wang , Hongyuan Fang , Lei Wang , Peng Zhao , Yanhui Pan
摘要: The present invention provides a rapid-hardening underground pipeline grouting repair polymer and a preparing method thereof for underground pipes. The rapid-hardening underground pipeline grouting repair polymer comprises the base resin and the hardener, weight ratio of which is 2:1-1:1. The base resin comprises 50 to 160 parts by weight of an isocyanate; 20 to 100 parts of a chlorophosphate mixture with a density over 1400 kg/m3; a parts by weight ratio of the isocyanate and chlorophosphate is 1:1-4:1. The hardener comprises 30 to 60 parts by weight of a chlorophosphate mixture with a density over 1400 kg/m3, 5 to 15 parts of a propyl formate, a methyl propionate or a mixture of a propyl formate and a methyl propionate, 15 to 55 parts of a polyol, 1 to 3 parts of a surfactant, 2 to 6 parts of a catalyst, 0 to 0.5 parts of water and 0 to 1 parts of a colorant.
-
-
-
-
-
-
-
-
-