An uninterruptible power supply (UPS) system (100) comprises a plurality of UPS units (UPS-1, UPS-2) connected in parallel. The controllers (130) of the units are programmed to implement a voltage calibration procedure and a current calibration procedure, in order that measurements of voltage and current made by sensors within the different units will agree. In the current calibration procedure, the load is disconnected (302) while one of the units is selected as a master and operates in a voltage control mode (VCM) (Steps 304-308). Each other unit is selected in turn and operated in a current control mode (310, 312). Current measurements made in the master unit are communicated (314) via a data bus to the selected unit and compared (316) with measurements made in the unit itself. The unit adapts its current sensing gains to match the master unit.
摘要:
Disclosed is a control circuit for control of a semiconductor switching device, such as an IGBT. The control circuit comprising a first feedback path between a first electrode and a control electrode of said semiconductor switching device which has a capacitance. The circuit is operable such that the capacitance in the first feedback path is dependent on the voltage level at said first electrode. In another embodiment the control circuit is operable such that a feedback signal begins to flow in the first feedback path immediately as the semiconductor switching device begins switching off, thereby causing a control action on the semiconductor switching device.
摘要:
A power reduction aggregation system for controlling and measuring power usage at a plurality of individual user locations which includes a plurality of power reduction controllers and a power reduction module. Each power reduction controller is disposed at one of the plurality of individual user locations and includes a controller module and an energy consumption module. The controller module is configured to selectively control power to a plurality of loads associated with each of the individual user locations. The energy consumption module is coupled to the controller module and is configured to determine energy reduction indicia associated with at least one of the plurality of loads. The power reduction module is communicatively coupled to each of the plurality of power reduction controllers and is configured to determine an aggregate energy reduction estimate by combining the energy reduction indicia determined by the plurality of power reduction controllers.
摘要:
A front-end converter in an uninterruptible power supply system is described. In an exemplary design, a front-end converter includes a boost circuit having first and second inputs, positive, negative, and neutral output nodes, an inductor, AC inputs, a battery, and first and second devices. The boost circuit is configured to provide a positive capacitor voltage between the positive and neutral nodes and to provide a negative capacitor voltage between the negative and neutral nodes. The first device selectively couples the inductor to a first AC input or a positive port of the battery and the second device selectively couples a negative port of the battery to the second input. The inductor is coupled to the first input and is shared between an online mode of the converter and an on-battery mode of the converter. The battery is coupled through the inductor to the first input during the on-battery mode.
摘要:
According to one aspect, embodiments of the invention provide a method of operating a UPS system having a first UPS, the method comprising powering on the first UPS, detecting a first signal at a first I/O of the first UPS using a first detection circuit of the first UPS, detecting a second signal at a second I/O of the first UPS using a second detection circuit of the first UPS, based on a status of the first signal and a status of the second signal, configuring the first UPS to operate in one of a master mode of operation and a controlled mode of operation.
摘要:
A system and method for providing a layout of equipment in a data center, the equipment including a plurality of equipment racks, and at least one rack-based cooling provider. In one aspect, the method includes receiving data regarding airflow consumption for each of the plurality of equipment racks and cooling capacity of the at least one cooling provider, determining a layout of the data center, displaying the layout of the data center. In the method determining a layout can include pairing each equipment rack of the plurality of equipment racks with another equipment rack of the plurality of equipment racks based on airflow consumption of each of the plurality of equipment racks to create a plurality of pairs of equipment racks, arranging the pairs of equipment racks to form a two-row cluster of equipment racks based on the airflow consumption value of the equipment racks.
摘要:
A power converter includes a battery having a positive terminal and a negative terminal, a first power input to receive AC input power, a second power input to receive DC input power from the battery, a first power output to charge the battery, a second power output to provide power to a load, a rectifier circuit coupled to the first power input, and a non-isolated single-stage power conversion circuit having an input and configured as a buck-boost converter. The power at the second power output is derived from the first power input and/or the second power input. The single-stage power conversion circuit is configured to convert an AC voltage to a DC voltage using a common energy storage element, and is coupled to the first power output and the rectifier circuit.
摘要:
Systems and method for installing computer equipment and power distribution equipment in facilities is provided. In one aspect, the present invention provides a power distribution rack, and uninterruptible power supply rack and a plurality of equipment racks. A plurality of power cables are run from the power distribution rack to each of the plurality of equipment racks using power cable tracks located on the roofs of the equipment racks.
摘要:
A method of optimizing power loads of a power strip is disclosed. The power strip includes single or three phase power input, a plurality of circuit breakers, and a plurality of outlets, with at least one circuit breaker being associated with at least one outlet. The method includes: obtaining real-time current measurements for each phase of the single or three phase power input of the power strip; obtaining real-time current measurements for each circuit breaker of the plurality of circuit breakers of the power strip; logging the real-time current measurements for each phase of the single or three phase power input and for each circuit breaker of the plurality of circuit breakers; and analyzing the real-time current measurements of the single or three phase power input and the plurality of circuit breakers to determine a preferential order of outlets in which to apply a new load.
摘要:
A method of calculating sensible cooling capacity of a cooling unit includes obtaining compressor capacity, subtracting compressor heat loss from the compressor capacity, subtracting latent cooling capacity from compressor capacity, and subtracting fan power loss from the compressor capacity. Methods of controlling a cooling unit and embodiments of a cooling unit are further disclosed.